Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be: 5.2.1 Permits and applicable regulations as may be provided by law or that govern the site; 5.2.2 Amendments and Change Orders; 5.2.3 Agreement; 5.2.4 Addenda and Bulletins; 5.2.5 Supplementary General Conditions; 5.2.6 General Conditions; 5.2.7 Plans; 5.2.8 Specifications; and 5.2.9 Attachments and Appendices.
Appears in 4 contracts
Sources: Construction Contract, Construction Manager at Risk Construction Agreement, Construction Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
5.2.1 5.3.1. Permits and applicable regulations as may be provided by law or that govern the site;
5.2.2 5.3.2. Amendments and Change Orders;
5.2.3 5.3.3. Construction Contract Agreement;
5.2.4 5.3.4. Design Contract Agreement;
5.3.5. Proposal, as accepted by OWNER;
5.3.6. Addenda and Bulletins;
5.2.5 Supplementary 5.3.7. Special Provisions;
5.3.8. Supplemental General Conditions;
5.2.6 5.3.9. General Conditions;
5.2.7 5.3.10. Plans;
5.2.8 5.3.11. Standard Plans;
5.3.12. Standard Specifications; and
5.2.9 Attachments 5.3.13. Reference Specifications, Attachments, and Appendices.
Appears in 1 contract
Sources: Design Build Construction Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
5.2.1 5.3.1. Permits and applicable regulations as may be provided by law or that govern the site;
5.2.2 5.3.2. Amendments and Change Orders;
5.2.3 5.3.3. Construction Contract Agreement;
5.2.4 5.3.4. Design Contract Agreement;
5.3.5. Proposal, as accepted by Owner;
5.3.6. Addenda and Bulletins;
5.2.5 Supplementary 5.3.7. Special Provisions;
5.3.8. Supplemental General Conditions;
5.2.6 5.3.9. General Conditions;
5.2.7 5.3.10. Plans;
5.2.8 5.3.11. Standard Plans;
5.3.12. Standard Specifications; and
5.2.9 Attachments 5.3.13. Reference Specifications, Attachments, and Appendices.
Appears in 1 contract
Sources: Construction Services Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
5.2.1 5.3.1. Permits and applicable regulations as may be provided by law or that govern the site;
5.2.2 5.3.2. Amendments and Change Orders;
5.2.3 5.3.3. Agreement;
5.2.4 5.3.4. Proposal, as accepted by Owner;
5.3.5. Addenda and Bulletins;
5.2.5 Supplementary 5.3.6. Special Provisions;
5.3.7. Supplemental General Conditions;
5.2.6 5.3.8. General Conditions;
5.2.7 5.3.9. Plans;
5.2.8 5.3.10. Standard Plans;
5.3.11. Standard Specifications; and
5.2.9 Attachments 5.3.12. Reference Specifications, Attachments, and Appendices.