Progress and Completion Schedules. If the progress of the Work is such that it appears to UGAA likely that the then-current, approved Project Schedule cannot or may not be met or that the then-current Contractual Date of Substantial Completion cannot or may not be achieved, Design-Builder shall attach to each Interim Payment Application a proposed “Progress and Completion Schedule” showing historic progress of the Work to-date, the timing and sequence of Work to be performed, future Milestone Dates, and other Schedule Data, all of which shall indicate Design-Builder’s intended plan for completing the Work on or before the Contractual Date of Substantial Completion. a. As-built and anticipated Work noted. Progress and Completion Schedules shall contain all the Schedule Data required in other schedules, including CPM data. The as-built portion of the Progress and Completion Schedule shall accurately reflect historic progress of the Work. The portion of it showing planned Work shall to be resource-loaded to indicate the performance required of the Design- Builder to complete the Work within the Contract Time.
Appears in 3 contracts
Sources: Standard Form of Agreement, Design Build Agreement, Construction Contract
Progress and Completion Schedules. If the progress of the Work is such that it appears to UGAA likely that the then-current, approved Project Schedule cannot or may not be met or that the then-current Contractual Date of Substantial Completion cannot or may not be achieved, Design-Builder CM shall attach to each Interim Payment Application a proposed “Progress and Completion Schedule” showing historic progress of the Work to-date, the timing and sequence of Work to be performed, future Milestone Dates, and other Schedule Data, all of which shall indicate Design-BuilderCM’s intended plan for completing the Work on or before the Contractual Date of Substantial Completion.
a. As-built and anticipated Work noted. Progress and Completion Schedules shall contain all the Schedule Data required in other schedules, including CPM data. The as-built portion of the Progress and Completion Schedule shall accurately reflect historic progress of the Work. The portion of it showing planned Work shall to be resource-loaded to indicate the performance required of the Design- Builder CM to complete the Work within the Contract Time.
Appears in 1 contract
Progress and Completion Schedules. If the progress of the Work is such that it appears to UGAA likely that the then-current, approved Project Schedule cannot or may not be met or that the then-current Contractual Date of Substantial Completion cannot or may not be achieved, Design-Builder Contractor shall attach to each Interim Payment Application a proposed “Progress and Completion Schedule” showing historic progress of the Work to-date, the timing and sequence of Work to be performed, future Milestone Dates, and other Schedule Data, all of which shall indicate Design-BuilderContractor’s intended plan for completing the Work on or before the Contractual Date of Substantial Completion.
a. As-built and anticipated Work noted. Progress and Completion Schedules shall contain all the Schedule Data required in other schedules, including CPM data. The as-built portion of the Progress and Completion Schedule shall accurately reflect historic progress of the Work. The portion of it showing planned Work shall to be resource-loaded to indicate the performance required of the Design- Builder Contractor to complete the Work within the Contract Time.
Appears in 1 contract
Sources: Construction Contract