PROGRESS OF WORK. a. Consultant shall prosecute the Work in a diligent and continuous manner and in accordance with all applicable notice to proceed, critical path schedule and guaranteed completion date requirements set forth in (or developed and agreed by the parties in accordance with) the Scope of Services. b. Consultant shall conduct regular meetings to update UTA's Project Manager regarding the progress of the Work including, but not limited to, any unusual conditions or critical path schedule items that could affect or delay the Work. Such meetings shall be held at intervals mutually agreed to between the parties. c. Consultant shall deliver monthly progress reports and provide all Contract submittals and other deliverables as specified in the Scope of Services. d. Any drawing or other submittal reviews to be performed by UTA in accordance with the Scope of Services are for the sole benefit of UTA and shall not relieve Consultant of its responsibility to comply with the Contract requirements. e. UTA will have the right to inspect, monitor and review any Work performed by consultant ▇▇▇▇▇▇▇▇▇ as deemed necessary by UTA to verify that such Work conforms to the Contract requirements. Any such inspection, monitoring and review performed by UTA is for the sole benefit of UTA and shall not relieve Consultant of its responsibility to comply with the Contract requirements. f. UTA shall have the right to reject Work which fails to conform to the requirements of this Contract. Upon receipt of notice of rejection from UTA, Consultant shall (at its sole expense and without entitlement to equitable schedule relief) promptly re-perform, replace or re-execute the Work so as to conform to the Contract requirements. g. If Consultant fails to promptly remedy rejected Work as provided in Section 3.F, UTA may (without limiting or waiving any rights or remedies it may have) perform necessary corrective action using other Consultants or UTA’s own forces. Any costs reasonably incurred by UTA in such corrective action shall be chargeable to Consultant.
Appears in 1 contract
Sources: Professional Services Agreement
PROGRESS OF WORK. a. Consultant Contractor shall prosecute the Work in a diligent and continuous manner and in accordance with all applicable notice to proceed, critical path schedule and guaranteed completion date requirements set forth in (or developed and agreed by the parties in accordance with) the Scope of Services.
b. Consultant Contractor shall conduct regular meetings to update UTA's Project Manager regarding the progress of the Work including, but not limited to, any unusual conditions or critical path schedule items that could affect or delay the Work. Such meetings shall be held at intervals mutually agreed to between the parties.
c. Consultant Contractor shall deliver monthly progress reports and provide all Contract submittals and other deliverables as specified in the Scope of Services.
d. Any drawing or other submittal reviews to be performed by UTA in accordance with the Scope of Services are for the sole benefit of UTA UTA, and shall not relieve Consultant Contractor of its responsibility to comply with the Contract requirements.
e. UTA will have the right to inspect, monitor and review any Work performed by consultant ▇▇▇▇▇▇▇▇▇ Contractor hereunder as deemed necessary by UTA to verify that such Work conforms to the Contract requirements. Any such inspection, monitoring and review performed by UTA is for the sole benefit of UTA UTA, and shall not relieve Consultant Contractor of its responsibility to comply with the Contract requirements.
f. UTA shall have the right to reject Work which fails to conform to the requirements of this Contract. Upon receipt of notice of rejection from UTA, Consultant Contractor shall (at its sole expense and without entitlement to equitable schedule relief) promptly re-perform, replace or re-execute the Work so as to conform to the Contract requirements.
g. If Consultant Contractor fails to promptly remedy rejected Work as provided in Section 3.F3.6, UTA may (without limiting or waiving any rights or remedies it may have) perform necessary corrective action using other Consultants contractors or UTA’s own forces. Any costs reasonably incurred by UTA in such corrective action shall be chargeable to ConsultantContractor.
Appears in 1 contract
Sources: Construction Services Agreement
PROGRESS OF WORK. a. Consultant shall prosecute the Work in a diligent and continuous manner and in accordance with all applicable notice to proceed, critical path schedule and guaranteed completion date requirements set forth in (or developed and agreed by the parties in accordance with) the Scope of Services.
b. Consultant shall conduct regular meetings to update UTA's Project Manager regarding the progress of the Work including, but not limited to, any unusual conditions or critical path schedule items that could affect or delay the Work. Such meetings shall be held at intervals mutually agreed to between the parties.
c. Consultant shall deliver monthly progress reports and provide all Contract submittals and other deliverables as specified in the Scope of Services.
d. Any drawing or other submittal reviews to be performed by UTA in accordance with the Scope of Services are for the sole benefit of UTA UTA, and shall not relieve Consultant of its responsibility to comply with the Contract requirements.
e. UTA will have the right to inspect, monitor and review any Work performed by consultant ▇▇▇▇▇▇▇▇▇ Consultant hereunder as deemed necessary by UTA to verify that such Work conforms to the Contract requirements. Any such inspection, monitoring and review performed by UTA is for the sole benefit of UTA UTA, and shall not relieve Consultant of its responsibility to comply with the Contract requirements.
f. UTA shall have the right to reject Work which fails to conform to the requirements of this Contract. Upon receipt of notice of rejection from UTA, Consultant shall (at its sole expense and without entitlement to equitable schedule relief) promptly re-perform, replace or re-re- execute the Work so as to conform to the Contract requirements.
g. If Consultant fails to promptly remedy rejected Work as provided in Section 3.F, UTA may (without limiting or waiving any rights or remedies it may have) perform necessary corrective action using other Consultants or UTA’s own forces. Any costs reasonably incurred by UTA in such corrective action shall be chargeable to Consultant.
Appears in 1 contract
Sources: Professional Services Agreement
PROGRESS OF WORK. a. Consultant Contractor shall prosecute the Work in a diligent and continuous manner and in accordance with all applicable notice to proceed, critical path schedule and guaranteed completion date requirements set forth in (or developed and agreed by the parties in accordance with) the Scope of Services.
b. Consultant Contractor shall conduct regular meetings to update UTA's Project Manager regarding the progress of the Work including, but not limited to, any unusual conditions or critical path schedule items that could affect or delay the Work. Such meetings shall be held at intervals mutually agreed to between the parties.
c. Consultant Contractor shall deliver monthly progress reports and provide all Contract submittals and other deliverables as specified in the Scope of Services.
d. Any drawing or other submittal reviews to be performed by UTA in accordance with the Scope of Services are for the sole benefit of UTA UTA, and shall not relieve Consultant Contractor of its responsibility to comply with the Contract requirements.
e. UTA will have the right to inspect, monitor and review any Work performed by consultant ▇▇▇▇▇▇▇▇▇ Contractor hereunder as deemed necessary by UTA to verify that such Work conforms to the Contract requirements. Any such inspection, monitoring and review performed by UTA is for the sole benefit of UTA UTA, and shall not relieve Consultant Contractor of its responsibility to comply with the Contract requirements.
f. UTA shall have the right to reject Work which fails to conform to the requirements of this Contract. Upon receipt of notice of rejection from UTA, Consultant Contractor shall (at its sole expense and without entitlement to equitable schedule relief) promptly re-perform, replace or re-execute the Work so as to conform to the Contract requirements.
g. If Consultant Contractor fails to promptly remedy rejected Work as provided in Section 3.F4.6, UTA may (without limiting or waiving any rights or remedies it may have) perform necessary corrective action using other Consultants contractors or UTA’s own forces. Any costs reasonably incurred by UTA in such corrective action shall be chargeable to ConsultantContractor.
Appears in 1 contract
Sources: Task Ordering Agreement