Progress Payment Certificate. Texas Department of Transportation RFP Addendum 12 Horseshoe Project 89 Design-Build Agreement August 29,September 17, 2012 (a) Upon receipt of TxDOT’s response under Section 12.4.6, DB Contractor may request TxDOT to execute and deliver to DB Contractor, within ten business days, a Progress Payment Certificate in a form substantially similar to Exhibit 21, identifying a total undisputed amount owing to DB Contractor, acknowledging its obligation to pay that amount to DB Contractor and committing to make payments to satisfy that obligation in accordance with the schedule described in Section 12.4.6. (b) Notwithstanding any other provision in this Agreement, DB Contractor may assign all or any portion of its rights, title and interests in and to the Progress Payment Certificate described in Section 12.7(a), or to any other payment made or owed by TxDOT under this Agreement, to any Person from which DB Contractor obtains financing to complete any portion of the Work. (c) At DB Contractor’s request, TxDOT will provide subsequent certificates to the extent appropriate to reflect additional undisputed amounts determined after issuance of the initial certificate to be owing to DB Contractor. Texas Department of Transportation RFP Addendum 12 Horseshoe Project 90 Design-Build Agreement August 29,September 17, 2012
Appears in 1 contract
Sources: Design Build Agreement
Progress Payment Certificate. Texas Department of Transportation RFP Addendum 12 23 Horseshoe Project 89 Design-Build Agreement August 29,September 17September 17,20, 2012
(a) Upon receipt of TxDOT’s response under Section 12.4.6, DB Contractor may request TxDOT to execute and deliver to DB Contractor, within ten business days, a Progress Payment Certificate in a form substantially similar to Exhibit 21, identifying a total undisputed amount owing to DB Contractor, acknowledging its obligation to pay that amount to DB Contractor and committing to make payments to satisfy that obligation in accordance with the schedule described in Section 12.4.6.
(b) Notwithstanding any other provision in this Agreement, DB Contractor may assign all or any portion of its rights, title and interests in and to the Progress Payment Certificate described in Section 12.7(a), or to any other payment made or owed by TxDOT under this Agreement, to any Person from which DB Contractor obtains financing to complete any portion of the Work.
(c) At DB Contractor’s request, TxDOT will provide subsequent certificates to the extent appropriate to reflect additional undisputed amounts determined after issuance of the initial certificate to be owing to DB Contractor. Texas Department of Transportation RFP Addendum 12 23 Horseshoe Project 90 Design-Build Agreement August 29,September 17September 17,20, 2012
Appears in 1 contract
Sources: Design Build Agreement