Eligible Changes Sample Clauses
Eligible Changes. 10.3.1.1 DB Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows:
(a) Additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) Additional costs relating to Hazardous Materials, Force Majeure Events, and damage to the Project, to the extent provided in Section 10.8; and
(c) Additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.7.3.
10.3.1.2 DB Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 10 and elsewhere in the CMA Documents, and furthermore is subject to DB Contractor’s compliance with all notification and other requirements identified herein. DB Contractor shall initiate the Change Order process by delivery of a PCO Notice as described in Section 10.3.2, followed by submittal of a Request for Change Order and supporting documentation to TxDOT.
Eligible Changes. 10.3.1.1 Maintenance Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows:
(a) additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) additional costs relating to Hazardous Materials, and Force Majeure Events, to the extent provided in Section 10.8.1; and
(c) additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.7.3.
10.3.1.2 Maintenance Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 10 and elsewhere in the CMA Documents, and furthermore is subject to Maintenance Contractor’s compliance with all notification and other requirements identified herein. Maintenance Contractor shall initiate the Change Order process by delivery of a PCO Notice as described in Section 10.3.2, followed by submittal of a Request for Change Order and supporting documentation to TxDOT.
Eligible Changes. 13.3.1.1. DB Contractor may request a Change Order to extend a Completion Deadline only for delays directly attributable to one or more of the following events or circumstances which change the duration of a Critical Path:
(a) Force Majeure Events;
(b) TxDOT-Caused Delays;
(c) delays relating to ROW acquisition by TxDOT, to the extent permitted by Section 6.4.1;
(d) delays relating to Utilities, to the extent permitted by Sections 6.8.1, 6.8.5 and 13.8.2;
(e) delays relating to Differing Site Conditions or discovery of Hazardous Materials, to the extent permitted by Section 13.8.
13.3.1.2. DB Contractor may request a Change Order to increase the Price only for increased costs of performance of the Work as follows:
(a) subject to Section 13.2.3, additional costs directly attributable to additional Work resulting from TxDOT-Directed Changes and TxDOT-Caused Delays for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) additional costs relating to Differing Site Conditions, Hazardous Materials, and Force Majeure Events, to the extent provided in Section 13.8;
(c) certain additional costs relating to Utility Adjustment Work, as described in Section 6.8 and Section 13.8.2, to the extent provided therein;
(d) additional costs directly attributable to uncovering, removing and restoring Work, to the extent provided in Section 5.4.3;
(e) Price adjustments as specified in Section 12.1; or
(f) additional costs for Utility Adjustment Work directly attributable to Necessary Basic Configuration Changes, to the extent provided in Section 13.8.
13.3.1.3. DB Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 13 and elsewhere in the Contract Documents, and furthermore is subject to DB Contractor’s compliance with all notification and other requirements identified herein. DB Contractor shall initiate the Change Order process by delivery of a PCO Notice as described in Section 13.3.2, followed by submittal of a Request for Change Order and supporting documentation to TxDOT.
Eligible Changes. DB Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows:
(a) additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) additional costs relating to Force Majeure Events, Hazardous Materials, Non- Discriminatory Changes and Damage to the Project, to the extent provided in Section 4.5.11; and
(c) additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.9.1.2.
Eligible Changes. 13.3.1.1. Contractor may request a Change Order to extend a Completion Deadline only for delays directly attributable to one or more of the following events or circumstances which change the duration of a Critical Path: (a) Force Majeure Events; (b) TxDOT-
13.3.1.2. DB Contractor may request a Change Order to increase the Price only for increased costs of performance of the Work as follows: (a) additional costs directly attributable to additional Work resulting from TxDOT-Directed Changes and TxDOT-Caused Delays for which TxDOT has not submitted a Change Order or a Request for Change Proposal; (b) additional costs relating to Differing Site Conditions, Force Majeure Events, Hazardous Materials to the extent provided in Section 13.7; (c) certain additional costs relating to Utility Adjustment Work, as described in Section 6.5 and Section 13.7.2, to the extent provided therein; (d) additional costs directly attributable to uncovering, removing and restoring Work, to the extent provided in Section 5.4.3; or (e) Price adjustments as specified in Section 12.1.
13.3.1.3. DB Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 13 and elsewhere in the DBA Documents, and furthermore is subject to DB Contractor’s compliance with all notification and other requirements identified herein. DB Contractor shall initiate the Change Order process by delivery of a PCO Notice as described in Section 13.3.2, followed by submittal of a Request for Change Order and supporting documentation to TxDOT.
Eligible Changes. This section outlines when Design-Builder shall submit a Change Notice and Request for Change Order to VPRA. Design-Builder shall use this process to request an adjustment to the Contract Price or a Completion Deadline due to a Relief Event. All Relief Events are subject to the limitations stated in this Article 12 in addition to any limitations stated in the definition of each Relief Event or elsewhere in the Contract Documents. Other than for the Relief Events herein, Design-Builder shall not be entitled to any adjustment of the Contract Price or a Completion Deadline. With respect to any request for relief, Design-Builder shall bear the burden of proving that it is entitled to the relief sought.
Eligible Changes. 10.3.1.1. Maintenance Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows:
(a) Additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) Additional costs relating to Hazardous Materials, Force Majeure Events and Non- Discriminatory ▇&▇ Changes, to the extent provided in Section 10.8; and
(c) Additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.7.3.
10.3.1.2. Maintenance Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 10 and elsewhere in the COMA Documents, and furthermore is subject to Maintenance Contractor’s compliance with all notification and other requirements identified herein. Maintenance Contractor shall initiate the Change Order process by delivery of a PCO Notice as described in Section 10.3.2, followed by submittal of a Request for Change Order and supporting documentation to TxDOT.
Eligible Changes. 10.3.1.1 Maintenance Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows:
(a) additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) additional costs relating to Hazardous Materials, and Force Majeure Events, to the extent provided in Section 10.8.1; and
(c) additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.7.3.
10.3.1.2 Maintenance Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 10 and elsewhere in the CMA Documents, and furthermore is subject to Maintenance Contractor’s compliance with all notification and other requirements identified herein. Maintenance Texas Department of Transportation US 77 from Kingsville to Driscoll November 15, 2012 41 Capital Main RFP Addendum 4 tenance Agreement Contractor shall initiate the Change Order process by delivery of a PCO Notice as described in Section 10.3.2, followed by submittal of a Request for Change Order and supporting documentation to TxDOT.
Eligible Changes. 10.3.1.1 Maintenance Contractor may request a Change Order to increase the Maintenance Price only for increased costs of performance of the Maintenance Services as follows:
(a) additional costs directly attributable to additional Maintenance Services resulting from TxDOT-Directed Changes for which TxDOT has not submitted a Change Order or a Request for Change Proposal;
(b) additional costs relating to Hazardous Materials, and Force Majeure Events, to the extent provided in Section 10.8.1; and
(c) additional costs directly attributable to uncovering, removing and restoring the work, to the extent provided in Section 5.7.3.
10.3.1.2 Maintenance Contractor’s entitlement to a Change Order for eligible changes is subject to the restrictions and limitations contained in this Section 10 and elsewhere in the CMA Documents, and furthermore is subject to Maintenance Contractor’s
Eligible Changes. Integrator may request a Change Order to extend a Completion Deadline only for delays directly attributable to one or more of the following events or circumstances which change the duration of a Critical Path: