Project Commissioning Plan. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedure the Contractor intends to use to ensure that Equipment is brought through pre-commissioning, commissioning, Start Up, Performance Tests and Substantial Completion of Project 5 safely and in accordance with Attachment 22 of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum: a. Mechanical completion; b. Field testing; c. Introduction of energy, power, hydrocarbons, refrigerants, etc. d. Commissioning including commissioning procedure; e. Ready for Start Up; f. Development of operating manuals; g. Development of maintenance manuals; h. Ready for Performance Testing; i. Performance Testing; j. Emissions and noise testing; k. Interface with the regulatory agencies as required in accordance with Section 9; l. Substantial Completion Punchlist for Project 5; m. Close-out; and
Appears in 1 contract
Project Commissioning Plan. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedure the Contractor intends to use to ensure that Equipment is brought through pre-commissioning, commissioning, Start Up, Performance Tests and Substantial Completion of Project 5 4 safely and in accordance with Attachment 22 of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum:
a. Mechanical completion;
b. Field testing;
c. Introduction of energy, power, hydrocarbons, refrigerants, etc.
d. Commissioning including commissioning procedure;
e. Ready for Start Up;
f. Development of operating manuals;
g. Development of maintenance manuals;
h. Ready for Performance Testing;
i. Performance Testing;
j. Emissions and noise testing;
k. Interface with the regulatory agencies as required in accordance with Section 9;
l. Substantial Completion Punchlist for Project 54;
m. Close-out; and