Common use of Project Completion Clause in Contracts

Project Completion. § 3.6.6.1 The Architect, assisted by the Construction Manager, shall: .1 conduct inspections to determine the date of Substantial Completion and the date of final completion;

Appears in 6 contracts

Sources: Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect

Project Completion. § 3.6.6.1 The Architect, assisted by the Construction Manager, Architect shall: .1 conduct inspections to determine the date or dates of Substantial Completion and the date of final completion;

Appears in 5 contracts

Sources: Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect

Project Completion. § 3.6.6.1 6.6.1 The ArchitectArchitect and its consultants, assisted by the Construction Manageras appropriate, shall: : .1 conduct inspections to determine the date or dates of Substantial Completion and the date of final completion;

Appears in 2 contracts

Sources: Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect

Project Completion. § 3.6.6.1 The Architect, assisted by the Construction Manager, Architect shall: .1 conduct inspections site observation to determine the date or dates of Substantial Completion and the date of final completion;

Appears in 2 contracts

Sources: Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect

Project Completion. § 3.6.6.1 The Architect, assisted by the Construction Manager, Architect Engineer shall: .1 conduct inspections to determine the date or dates of Substantial Completion and the date of final completion;

Appears in 2 contracts

Sources: Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect

Project Completion. § 3.6.6.1 The Architect, assisted by the Construction Manager, Architect shall:: and repon a uments late fina . .1 conduct inspections to determine recommend the date or dates of Substantial Completion and the date of final completion;

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Architect

Project Completion. § 3.6.6.1 2.6.6.1 The Architect, assisted by the Construction Manager, Architect Engineer shall: .1 conduct inspections to determine the date or dates of Substantial Completion and the date of final completion;

Appears in 1 contract

Sources: Architect's Services Agreement

Project Completion. § 3.6.6.1 The On behalf of the Owner, the Architect, assisted by the Construction Manager, shall: .1 conduct inspections to determine the date of Substantial Completion and the date of final completion;

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Architect

Project Completion. § 3.6.6.1 3.7.6.1 The Architect, assisted by the Construction Manager, Architect shall: .1 conduct inspections to determine the date or dates of Substantial Completion and the date of final completion;

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Architect

Project Completion. § 3.6.6.1 6.6.1 The ArchitectArchitect and its consultants, assisted by the Construction Manageras appropriate, shall: .1 conduct inspections to determine the date or dates of Substantial Completion and the date of final completion;

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Architect

Project Completion. § 3.6.6.1 The Architect, assisted by the Construction Manager, Architect shall: .1 conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; .2 issue Certificates of Substantial Completion;

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Architect

Project Completion. § 3.6.6.1 The Architect, assisted by in consultation with the Construction ManagerOwner, shall: : .1 conduct inspections to determine the date or dates of Substantial Completion and the date of final completion;

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Architect

Project Completion. § 3.6.6.1 2.6.6.1 The Architect, assisted by the Construction Manager, Architect shall: .1 conduct inspections to mutually determine with the Owner the date or dates of Substantial Completion and the date of final completion;

Appears in 1 contract

Sources: Architect's Services Agreement

Project Completion. § 3.6.6.1 The Architect, assisted by the Construction Manager, Architect shall: .1 conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; • .2 issue Certificates of Substantial Completion;

Appears in 1 contract

Sources: Aia B101 Standard Form of Agreement Between Owner and Architect