Project Completion. § 3.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the Contractor and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract Documents and assembled by the Contractor; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents. § 3.6.6.2 The Architect’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor of Work to be completed or corrected. § 3.6.6.3 When the Work is found to be substantially complete, the Architect shall inform the Owner about the balance of the Contract Sum remaining to be paid the Contractor, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work. § 3.6.6.4 The Architect shall forward to the Owner the following information received from the Contractor: (1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; (2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the Contractor under the Contract Documents. § 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion, the Architect shall, without additional compensation, conduct a meeting with the Owner to review the facility operations and performance.
Appears in 4 contracts
Sources: Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect (Nu Skin Enterprises Inc)
Project Completion. § 3.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the Contractor and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract Documents and assembled by the Contractor; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 The Architect’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor of Work to be completed or corrected.. the ing of final payment; (2)liens; and (3) any other Su
§ 3.6.6.3 When the Work is found to be substantially complete, the Architect shall inform the Owner about the balance of the Contract Sum remaining to be paid the Contractor, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 The Architect shall forward to the Owner the following information received from the Contractor: (1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; (2) mak affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the Contractor under the Contract Documents.
§ 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion, the Architect shall, without additional compensation, conduct a meeting with the Owner to review the facility operations and performance.of
Appears in 2 contracts
Sources: Standard Form of Agreement Between Owner and Architect for a Large or Complex Project, Standard Form of Agreement Between Owner and Architect for a Large or Complex Project
Project Completion. § 3.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the Substantia date of final completion; issue Certificates of Substantial Completion; receive from the Contractor and forward to Con the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract r Documents and assembled by the Contractor; and issue a final Certificate for Payment based upon a final inspection base indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 The Architect’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor of Work to be completed or corrected.
§ 3.6.6.3 When the Work is found to be substantially complete, the Architect shall inform advise the Owner about the balance of the Contract Sum remaining to be paid the Contractor, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 The Architect shall forward to the Owner the following information received from the Contractor: (1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; (2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the Contractor under the Contract Documents.
§ 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year ten (10) months from the date of Substantial Completion, the Architect shall, without additional compensation, conduct a meeting with the Owner to review the facility operations and performance.
Appears in 2 contracts
Sources: Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect
Project Completion. § 3.6.6.1 The Architect A/E shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the Contractor and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract Documents and assembled by the Contractor; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 The ArchitectA/E’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor of Work to be completed or corrected.
§ 3.6.6.3 When the Work is found to be substantially complete, the Architect A/E shall inform advise the Owner about the balance of the Contract Sum remaining to be paid the Contractor, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 The Architect A/E shall forward to the Owner the following information received from the Contractor: (1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; (2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the Contractor under the Contract Documents.
§ 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion, the Architect A/E shall, without additional compensation, conduct a meeting with the Owner to review the facility operations and performance.
Appears in 1 contract
Project Completion. § 3.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the Contractor CM and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract Documents and assembled by the ContractorCM; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 The Architect’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor CM of Work to be completed or corrected. The Architect’s final inspection shall be conducted with the Owner.
§ 3.6.6.3 When the Work is found to be substantially complete, the Architect shall inform the Owner about the balance of the Contract Sum remaining to be paid the ContractorCM, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 The Architect shall forward to the Owner the following information received from the ContractorCM: (1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; (2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the Contractor CM under the Contract Documents.
§ 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion, (anticipated to be October 2022), the Architect shall, without additional compensation, conduct a meeting with the Owner to review the facility operations and performance.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Architect
Project Completion. § 3.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the Contractor Construction Manager and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract Documents and assembled by the ContractorConstruction Manager; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 The Architect’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor Construction Manager of Work to be completed or corrected.
§ 3.6.6.3 When the Work is found to be substantially complete, the Architect shall inform the Owner about the balance of the Contract Sum remaining to be paid the ContractorConstruction Manager, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 The Architect shall forward to the Owner the following information received from the Contractor: Construction Manager:
(1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; ;
(2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the Contractor Construction Manager under the Contract Documents.
§ 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion, the Architect shall, without additional compensation, conduct a meeting with the Owner to review the facility operations and performance.
Appears in 1 contract
Sources: Architect and Consultant Agreement
Project Completion. § 3.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the Contractor and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract Documents and assembled by the Contractor; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 The Architect’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor of Work to be completed or corrected.submit
§ 3.6.6.3 When the Work is found to be substantially complete, the Architect shall inform the Owner about the balance of the Contract Sum remaining to be paid the Contractor, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 The Architect shall forward to the Owner the following information received from the Contractor: (1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; (2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the Contractor under the Contract Documents.
§ 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion, the Architect shall, without additional compensation, conduct a meeting with the Owner to review the facility operations and performance.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Architect
Project Completion. § 3.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the Contractor and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract Documents and assembled by the Contractor; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 The Architect’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor of Work to be completed or corrected.
§ 3.6.6.3 When the Work is found to be substantially complete, the Architect shall inform the Owner about the balance of the Contract Sum remaining to be paid the Contractor, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 The Architect shall forward to the Owner the following information received from the Contractor: (1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; (2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the Contractor under the Contract Documents.
§ 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion, the Architect shall, without additional compensation, conduct a meeting with the Owner and contractor to review the facility operations and performance.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Architect for a Large or Complex Project
Project Completion. § 3.6.6.1 5.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the Contractor and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract Documents and assembled by the Contractor; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 5.6.6.2 The Architect’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor of Work to be completed or corrected.
§ 3.6.6.3 5.6.6.3 When the Work is found to be substantially complete, the Architect shall inform the Owner about the balance of the Contract Sum remaining to be paid the Contractor, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 5.6.6.4 The Architect shall forward to the Owner the following information received from the Contractor: (1) consent of surety or sureties, if any, to reduction in or partial release of retainage retain-age or the making of final payment; (2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the Contractor under the Contract Documents.
§ 3.6.6.5 5.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion, the Architect shall, without additional compensation, conduct a meeting with the Owner to review the facility operations and performance.
Appears in 1 contract
Sources: Architectural Consultancy Agreement
Project Completion. § 3.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the Contractor Construction Manager and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract Documents and assembled by the ContractorConstruction Manager; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 The Architect’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor Construction Manager of Work to be completed or corrected.
§ 3.6.6.3 When the Work is found to be substantially complete, the Architect shall inform the Owner about the balance of the Contract Sum remaining to be paid the ContractorConstruction Manager, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 The Architect shall forward to the Owner the following information received from the Contractor: Construction Manager:
(1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; ;
(2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the Contractor Construction Manager under the Contract Documents.
§ 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion, the Architect shall, without additional compensation, conduct a meeting with the Owner to review the facility operations and performance.
§ 3.6.6.6 As part of Basic Services, at the completion of the Project, the Architect shall review and return to the Construction Manager or Contractor, for the benefit of the Owner and the Architect, a set of record drawings prepared by the Contractors which shall be a complete set of drawings marked as to show significant changes in the Work made during construction.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Architect
Project Completion. § 3.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the CM/GC Contractor and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract Documents and assembled by the CM/GC Contractor; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 The Architect’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the CM/GC Contractor of Work to be completed or corrected.
§ 3.6.6.3 When the Work is found to be substantially complete, the Architect shall inform the Owner about the balance of the Contract Sum remaining to be paid the CM/GC Contractor, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 The Architect shall forward to the Owner the following information received from the CM/GC Contractor: :
(1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; ;
(2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the CM/GC Contractor under the Contract Documents.
§ 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion, the Architect shall, without additional compensation, conduct a meeting with the Owner and CM/GC Contractor to review the facility operations and performance.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Architect
Project Completion. § 3.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the Contractor and forward to the OwnerTownship, for the OwnerTownship’s review and records, written warranties and related documents required by the Contract Documents and assembled by the Contractor; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 The Architect’s inspections shall be conducted with the Owner Township to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor of Work to be completed or corrected.
§ 3.6.6.3 When the Work is found to be substantially complete, the Architect shall inform the Owner about Township as to the balance of the Contract Sum remaining to be paid the Contractor, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 The Architect shall forward to the Owner Township the following information received from the Contractor: (1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; (2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner Township against liens; and (3) any other documentation required of the Contractor under the Contract Documents.
§ 3.6.6.5 Upon request of the OwnerTownship, and prior to the expiration of one year from the date of Substantial Completion, the Architect shall, without additional compensation, conduct a meeting with the Owner Township to review the facility operations and performance.
Appears in 1 contract
Sources: Architectural Services Agreement
Project Completion. § 3.6.6.1 The Architect shall conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion; receive from the Contractor Construction Manager and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract Documents and assembled by the ContractorConstruction Manager; and issue a final Certificate for Payment based upon a final inspection indicating the Work complies with the requirements of the Contract Documents.
§ 3.6.6.2 The Architect’s inspections shall be conducted with the Owner to check conformance of the Work with the requirements of the Contract Documents and to verify the accuracy and completeness of the list submitted by the Contractor Construction Manager of Work to be completed or corrected.
§ 3.6.6.3 When the Work is found to be substantially complete, the Architect shall inform the Owner about the balance of the Contract Sum remaining to be paid the ContractorConstruction Manager, including the amount to be retained from the Contract Sum, if any, for final completion or correction of the Work.
§ 3.6.6.4 The Architect shall forward to the Owner the following information received from the ContractorConstruction Manager: (1) consent of surety or sureties, if any, to reduction in or partial release of retainage or the making of final payment; (2) affidavits, receipts, releases and waivers of liens or bonds indemnifying the Owner against liens; and (3) any other documentation required of the Contractor under the Contract Documents.
§ 3.6.6.5 Upon request of the Owner, and prior to the expiration of one year from the date of Substantial Completion, the Architect shall, without additional compensation, conduct a meeting with the Owner to review the facility operations and performance.and
Appears in 1 contract
Sources: Architectural Services Agreement