Project Criteria. 5.3.1 Design-Builder shall meet with Owner Parties to discuss its preliminary evaluation of the Project Criteria (the “Preliminary Evaluation Meeting”) during which Design-Builder shall address (a) possible alternative approaches to design and construction of the Project and recommend when appropriate accelerated or fast-track scheduling, procurement, or phased construction and (b) cost information, constructability, and procurement and Project scheduling issues. 5.3.2 Within ten (10) Days of the Preliminary Evaluation Meeting, Design-Builder shall report in writing to Owner Parties with a summary of its understanding and a plan for implementation of the Project Criteria (the “Preliminary Design Report”), including: (i) a preliminary Estimated Project Sum and recommendations for meeting or adjusting the Project Criteria to conform to the Owner’s budget;