Project Specific Milestones Sample Clauses

POPULAR SAMPLE Copied 1 times
Project Specific Milestones. During the term of this WMPA, Wholesale Market Participant shall ensure that it meets each of the following milestones: 3.1.1 Substantial Site work completed. On or before November 28, 2022
Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before March 31, 2016 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities.
Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones:
Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before July 1, 2021, Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.2 Delivery of major electrical equipment. On or before July 15, 2021, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.
Project Specific Milestones. During the term of this WMPA, Wholesale Market Participant shall ensure that it meets each of the following milestones:
Project Specific Milestones. In addition to the milestones stated in GIP, section [to be determined], as applicable, during the term of this GIA, Project Developer shall ensure that it meets each of the following development milestones: [As appropriate include the following standard Milestones, with any revisions necessary for the project at hand (sections should be renumbered as appropriate):] 6.1 Substantial Site work completed. On or before , Project Developer must demonstrate completion of at least 20% of project site construction. At this time, Project Developer must submit to Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Project Developer Interconnection Facilities.
Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Local, county and state site permits. Interconnection Customer must obtain all necessary local, county and state site permits by January 31, 2021. 6.2 Substantial Site work completed. On or before November 30, 2021 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.3 Delivery of major electrical equipment. On or before November 30, 2021, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.
Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Site Permits. On or before July 15, 2022, Interconnection Customer must demonstrate that it has obtained any necessary local, county, and state site permits. 6.2 Acquisition of major electrical equipment. On or before January 15, 2023, Interconnection Customer must demonstrate that it has signed a memorandum of understanding for the acquisition of major electrical equipment. 6.3 Substantial Site work completed. On or before February 15, 2024, Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.4 Delivery of major electrical equipment. On or before January 15, 2024, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.
Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. Not applicable for this project. 6.2 Delivery of major electrical equipment. Not applicable for this project.
Project Specific Milestones. In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Site permits. On or before September 30, 2022, Interconnection Customer must demonstrate that it has obtained all necessary local, county, and state site permits. 6.2 Acquisition of major electrical equipment. On or before October 31, 2022, Interconnection Customer must demonstrate that it has signed a memorandum of understanding for the acquisition of major equipment 6.3 Substantial Site work completed. On or before December 31, 2023 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.4 Delivery of major electrical equipment. On or before March 31, 2023, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.