Project Management (For All Phases. 8.1.1 The Owner’s Project Manager shall prepare a communication and document control procedure for the duration of the Project. This procedure shall detail the responsibilities and lines of communication among all Project participants (Owner, Owner’s Project Manager, Designer, Contractor, Subcontractors and other consultants, vendors or suppliers) and establish the procedure for correspondence, document control, designer and contractor submittal logs, change order reporting and other tracking logs, as needed. The draft communication plan shall be submitted to the Owner for approval within 30 days of the Approval to proceed to Construction Documents/Bidding Phase and be further updated as needed to include the award of a construction contract and/or no later than 30 days after Approval to Proceed to the Construction Phase. The Owner’s Project Manager shall include the Designer and the Contractor in its distribution of the Project Budget, Schedule, Monthly Progress Report and other reports as appropriate and as outlined in the Communications Plan. 8.1.1.1 The Owner’s Project Manager shall assist the Owner in the preparation of all information, material, documentation, and reports that may be required or requested by the Owner. 8.1.1.2 The Owner’s Project Manager shall prepare agendas for and attend building committee meetings, attend meetings with other representatives of the Owner, municipal administration and, and attend neighborhood meetings relating to the Project, and participate as a member of the Owner’s Prequalification Committee as applicable. The Owner’s Project Manager shall take minutes of all of the above-referenced meetings and promptly distribute minutes of these meetings to the Owner. 8.1.1.3 The Owner’s Project Manager shall review all applications for payments, requisitions and invoices relating to the Project as submitted by the Designer, General Contractor, equipment vendors and all other prime contractors and suppliers and make recommendations to the Owner relative to amounts due.
Appears in 1 contract
Project Management (For All Phases. 8.1.1 The Owner’s Project Manager shall prepare a communication and document control procedure for the duration of the Project. This procedure shall detail the responsibilities and lines of communication among all Project participants (Owner, Authority, Owner’s Project Manager, Designer, Contractor, Subcontractors and other consultants, vendors or suppliers) and establish the procedure for correspondence, document control, designer and contractor submittal logs, change order reporting and other tracking logs, as needed. The draft communication plan shall be submitted to the Owner for approval within 30 days of the Approval to proceed to Construction Documents/Bidding Phase and be further updated as needed to include the award of a construction contract and/or no later than 30 days after Approval to Proceed to the Construction Phase. The Owner’s Project Manager shall include the Designer and the Contractor in its distribution of the Project Budget, Schedule, Monthly Progress Report and other reports as appropriate and as outlined in the Communications Plan.
8.1.1.1 The Owner’s Project Manager shall assist the Owner in the preparation of all information, material, documentation, and reports that may be required or requested by the OwnerAuthority, including without limitation, documentation related to incentive reimbursement percentage points that may be awarded to the Owner by the Authority, requests for reimbursement, and audit materials.
8.1.1.2 The Owner’s Project Manager shall prepare agendas for and attend building committee meetings, attend meetings with other representatives of the Owner, municipal administration and, and attend neighborhood meetings relating to the Project, and participate as a member of the Owner’s Prequalification Committee as applicable. The Owner’s Project Manager shall take minutes of all of the above-referenced meetings and promptly distribute minutes of these meetings to the Owner.
8.1.1.3 The Owner’s Project Manager shall review all applications for payments, requisitions and invoices relating to the Project as submitted by the Designer, General Contractor, equipment vendors and all other prime contractors and suppliers and make recommendations to the Owner relative to amounts due.
Appears in 1 contract