Project Revisions. (a) Revisions to the project activities. Additions and changes to the scope of an approved project, including any requested funding increases, require submission of a revised project plan for TCEQ review and approval. These changes to an approved project will not take effect until the TCEQ has issued a revised NTP, approving and incorporating these changes. (b) Revisions to the project activities that do not affect the project budget categories, or cause an increase or decrease in the activities performed under the project may be approved by TCEQ as a minor change through electronic mail. (c) Revisions to the project budget. Cumulative transfers among the budgeted direct cost categories within a project budget must not exceed 10 percent (10%) of the current total budgeted amount for that project. Transfers exceeding 10% require submission of a revised project plan as detailed in (a) above.