Project Time Schedule Sample Clauses
The PROJECT TIME SCHEDULE clause establishes the timeline for completing various phases or milestones of a project. It typically outlines key deadlines, deliverable dates, and may specify procedures for adjusting the schedule if delays occur. This clause ensures that all parties are aware of their time-related obligations, helping to coordinate activities and manage expectations, thereby reducing the risk of disputes over project timing.
POPULAR SAMPLE Copied 3 times
Project Time Schedule. The parties agree that Developer shall be able to develop in accordance with Developer’s own time schedule as such schedule may exist from time to time, and Developer shall determine which part of the Project Site to develop first, and at Developer’s chosen schedule. In particular, and not in limitation of any of the foregoing, since the California Supreme Court held in ▇▇▇▇▇▇ Construction Co. v. City of Camarillo, 37 Cal.3d 465 (1984), that the failure of the parties therein to consider and expressly provide for the timing of development resulted in a later-adopted initiative restricting the timing of development to prevail over such parties’ agreement, it is the parties’ desire to avoid that result by acknowledging that Developer shall have the right to develop the Project in such order and at such rate and at such times as Developer deems appropriate within the exercise of its subjective business judgment. Developer’s rights under this Section 6.08(b) shall be subject to the requirement that adequate infrastructure to serve each phase of the Project is constructed concurrently with such phase. The City Manager shall reasonably determine what infrastructure will be required to serve each phase of the Project, which determination shall be consistent with Applicable Law.
Project Time Schedule. 3.1. The Beneficiary is bound to ensure the commencement of the Project execution not before the date the present Contract comes into force and no later than 5 months from the date this Contract is effective. The commencement date of the Project implementation is considered to be the very same date the employment contract concluded between the Beneficiary and the visiting scientist comes into force. The Beneficiary is obliged to notify the SAS in writing about the start date of the Project execution no later than 5 calendar days before that date, unless this date was agreed during the negotiation of the present Contract, or if the Project execution start date was agreed, however, the change has occurred.
3.2. The Beneficiary is bound immediately after the present Contract comes into force to commence performing all necessary administrative actions (such as, for example, actions leading to arrange the visiting scientist's visa if any, etc.), which guarantee compliance with the deadline for starting the Project implementation defined in Art. 3.1. of the Contract herein. The Beneficiary is also obliged to ensure that the all administration and administrative actions according to the previous sentence commence to be carried out by the Principal investigator of the Project immediately after this Contract comes into force. The Beneficiary and the Principal investigator are bound to provide each other with the necessary collaboration in course of activities under this Article herein the Contract.
3.3. In case the Beneficiary finds out that it will not be possible due to vis major to commence the Project implementation within the period specified in Art. 3.1. of the Contract herein, he/she is obliged to inform the SAS in writing with no delay about this fact. In such case, the SAS may allow an extension of the deadline for starting the Project implementation according to Art.
3.1. herein the Contract, however, not more than by 3 months, while considering the justification of the reasons resulting to the delayed start of the Project implementation.
3.4. For reasons of vis major, for the purpose of Art. 3.3. of the Contract herein are considered the following:
a) serious health reasons on the side of the visiting scientist, his/her spouse or his/her children,
b) death of the visiting scientist's spouse or child,
c) a natural disaster that demonstrably makes it impossible for the visiting scientist to arrive at the location of the Project implementation,
d) administr...
Project Time Schedule. After a "Notice to Proceed" and issuance of a Purchase Order(s), the Contractor shall commence the work within five (5) calendar days from the date of Work Order and continue all work in an expeditious manner to a conclusion acceptable to the Engineer. As time is an essential element of the contract, the Contractor is expected to supply sufficient work force material and equipment to perform the work listed under the "Scope of Work" in accordance with the schedule(s) approved by the Engineer and the requirements stipulated in the Contract Documents. All activities required to be performed to complete the Work, including site restoration and punch list items, shall be completed within the Contract time. Progress of the work shall be judged based on a proportion of the amount of work completed and accepted, to the number of calendar days that remain on the Contract. Contract work completed shall not fall behind by more than ten (10) percentage points, according to the total number of days past since the issue date of the Work Order(s). If the Contractor fails to complete all work under the contract within the time specified in the "Notice to Proceed" and/or Work Order(s), or fails to perform the work with sufficient personnel and equipment or with sufficient materials to assure the prompt completion of the work assigned, or discontinues the prosecution of the work, or fails to resume work which has been discontinued within a reasonable time after notice to do so, or becomes insolvent or is declared bankrupt, or files for reorganization under the bankruptcy or insolvency code, or for any other cause whatsoever, fails to carry on the work in an acceptable manner, or if the surety executing the bond, becomes unsatisfactory in the opinion of the City, the Engineer will give notice in writing to the Contractor and his surety of such delay, neglect, or default. Additionally, the City may opt to not issue further Work orders and/or to cancel the Contract.
Project Time Schedule. The Project Time Schedule is a chronological list of activities presenting the period of time anticipated to complete the work described in the Scope of Services. It begins on the date when a Notice to Proceed is issued and ends on a projected future date. The actual project ends on whichever of the following occurs last:
1. A notice of suspension or termination takes effect, or
2. The work is “satisfactorily completed and accepted” in accordance with applicable regulatory requirements and as defined by this Agreement, as amended by Supplemental Agreement and/or Extra Work Order(s).
Project Time Schedule. The Work shall be substantially complete by not later than _, unless the Owner and Contractor agree to a different completion date (“Substantial Completion”). For purposes of this Agreement, “Substantially Complete” means that the Work is complete in accordance with the Contract Documents so that the Owner may utilize the Work for its intended purpose, subject to minor punchlist items which Contractor shall complete within seven (7) days after attainment of substantial completion.
Project Time Schedule. The Owner anticipates that Work on the Project will begin upon its issuance of a Notice to Proceed and be completed by , unless the Owner and Contractor agree to different commencement and completion dates.
Project Time Schedule. Phase Estimated Time to Complete
Project Time Schedule. Year of 2008: Compensation and clearing of the ground 1B and construction of the access road to the plant will be carried out by the 2nd quarter of 2008.
Project Time Schedule. The City intends to begin this project upon Notice to Proceed. The expected time for completion of the project construction documents is twelve (12) months. All aspects of the project are outlined in the below listed Project Timeline.
Project Time Schedule. 2.6.1. THE ARCHITECT ACKNOWLEDGES THAT THE COMPLETION OF THE PROJECT SO AS TO MEET THE OWNER'S DESIGN AND OCCUPANCY REQUIREMENTS IS A PRIME CONSIDERATION OF THE OWNER AND THAT THE DATES WILL NOT BE CHANGED WITHOUT THE PRIOR WRITTEN APPROVAL OF THE OWNER. The Architect, after consultation with the Owner, will prepare a Preliminary Project Time Schedule, which is consistent with the Owner's requirements (as these are communicated to the Architect), and submit such schedule to the Owner during the Schematic Design Phase. The Preliminary Project Time Schedule will coordinate and integrate the Architect's design efforts with the proposed construction schedule. The Architect shall include within the Contract Documents requirements for the Contractor to submit a detailed Project Time Schedule for the execution of the Contractor's work, which Schedule shall be developed to meet the Owner's occupancy requirements. When the Architect believes the Contractor will not meet any of the significant dates within the Project Time Schedule, the Architect will advise the Owner of the options available to the Owner for maintaining the schedule. The Owner and the Architect are aware that many factors outside of the Architects control may affect the Architect’s ability to complete the services to be provided under this agreement. The Architect will perform these services with reasonable diligence and expediency consistent with sound professional practices. The owner agrees that the Architect is not responsible for damages arising directly or indirectly from any delays for causes beyond the Architects control. For purposes of this Agreement, such causes include, but are not limited to, strikes or other labor disputes; severe weather disruptions or other natural disasters or acts of God; fires, riots, war or other emergencies; failure of any government agency to act in a timely manner; failure of performance by the Owner or the Owner’s contractors or consultants; or discovery of any hazardous substances or differing site conditions. In addition, if the delays resulting from such causes increase the cost or time required by the Architect to perform it’s services in an orderly and efficient manner, the Architect shall be entitled to a reasonable adjustment in schedule and compensation.