Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority. 14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Project, if at least 90% (ninety percent) of the Project has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 4 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “"Provisional Certificate”") if the Tests are successful and the Project Bus Terminal and/ or Commercial Complex can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “"Punch List”"); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Concessioning Authority.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Project, if at least 9095% (ninety percent) of the Project Bus Terminal and mandatory Commercial Complex respectively has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 4 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Project, if at least 90the Concessionaire has completed construction of 100% (ninety percentHundred per cent) of the Project has been completedSite made available to the Concessionaire up to 182 days from the Appointed Date. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 4 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Project, if at least 90the Concessionaire has completed construction of 100% (ninety percentHundred per cent) of the Project has been completedSite made available to the Concessionaire up to [180 days]µ from the Appointed Date. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 3 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Project, if at least 90the Concessionaire has completed construction of 100% (ninety percentHundred per cent) of the Project has been completedSite made available to the Concessionaire up to 183 days from the Appointed Date. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 3 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project Highway can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is due to is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the ProjectProject Highway, if at least the Concessionaire has completed construction of 90% (ninety percentNinety per cent) of the Project has been completedSite made available to it up to 180 days from the Appointed Date. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 2 contracts
Sources: Model Concession Agreement, Model Concession Agreement
Provisional Certificate. 14.3.1 13.3.1. Subject to the provisions of Clause 14.3.213.3.2, the Independent Authority’s Chief Engineer may, at the request of the ConcessionaireConcessionaire and on the recommendations of the Independent Engineer, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “"Provisional Certificate”) "), if the Tests including the Trial Operations are successful and the Project can be safely and reliably placed in commercial operation operations though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Authority’s Chief Engineer and the Concessionaire (the “"Punch List”"); provided that the Independent Chief Engineer shall not withhold the Provisional Certificate for reason of any work remaining remain incomplete if the delay in completion thereof is attributable to the Authority.
14.3.2 13.3.2. The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 13.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Project, if at least 90the Concessionaire has completed construction of 100% (ninety percenthundred per cent) of the Project has been completedSite made available to the Concessionaire up to 30 days from the Appointed Date. Upon issue issuance of such Provisional Certificate, the provisions of Article 15 14 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project Bus Port can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is due to is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the ProjectProject Bus Port, if at least the Concessionaire has completed construction of 90% (ninety percentNinety per cent) of the Project has been completedProject. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J K (the “Provisional Certificate”) if the Tests are successful and the Project XXX Ropeway can be safely and reliably placed in commercial operation though certain associated works and / or things facilities for Users forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Projecta line, if at least 9075% (ninety seventy five percent) of the Project total length of such line has been completed. Upon issue of such Provisional Certificateprovisional certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 2 contracts
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the 14.3.1. The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet notyet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority.
14.3.2 14.3.2. The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request uponrequest of the Concessionaire to this effect, be issued for operating part of the Project, if at least 9075% (ninety percentseventy five per cent) of the total work of the Project has been completed. Provided further no such Provisional Certificate would be issued if the Concessionaire has not commenced the construction on the Site handed over to it within 120 days of the Appointed Date. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the 14.3.1. The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project Airport can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority.
14.3.2 14.3.2. The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the ProjectAirport, if at least 90% (ninety percent) of the Project has been completedit can be safely and reliably placed in commercial operation in accordance with the
1. Upon issue of such Provisional Certificate, the provisions of Article 15 this Agreement shall apply to such completed partpart of the Airport, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project Airport shall be construed accordingly.
Appears in 1 contract
Sources: Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate on completion of completion substantially 100% project length in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Project, if at least 90the Concessionaire has completed construction of 100% (ninety percentHundred per cent) of the Project has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply Site made available to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of up to 180 days from the Project shall be construed accordinglyAppointed Date.
Appears in 1 contract
Sources: Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Project, if at least 90the Concessionaire has completed construction of 100% (ninety percentHundred per cent) of the Project has been completedSite made available to the Concessionaire up to 219 days from the Appointed Date. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 1 contract
Sources: Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer Expert may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer Expert and the Concessionaire (the “Punch List”); provided that the Independent Engineer Expert shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Project, if at least 90% (ninety percentper cent) of the phase-1 of the Project has been completedcompleted and it can be safely and reliably be placed in commercial operation in accordance with the provisions of Clause 14.3.1. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and part of Project. The parties further agree that the rights and obligations of provisional certificate shall be issued separately for the Concessionaire for and in respect of such completed part subsequent phases of the Project shall be construed accordingly.with above mentioned conditions applicable separately for each phase. The details of the phasing of the project are mentioned in Schedule G.
Appears in 1 contract
Sources: Model Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the 14.1.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J Schedule 10 (the “Provisional Certificate”) if the Tests are successful and key activities indicated in the Implementation Schedule have been successfully completed post which the Project Facilities can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch list shall also include the cost of completion of each of the outstanding items.
14.3.2 14.1.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 Article 14.1 may, upon request of the Concessionaire to this effect, be issued for operating part of the ProjectAdditional Project Facilities, if at least 90% (ninety percentper cent) of the Additional Project Facilities has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 1 contract
Sources: Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the 14.1.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J Schedule 10 (the “Provisional Certificate”) if the Tests are successful and key activities indicated in the Implementation Schedule have been successfully completedpost which the Project Facilities can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided List”);provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch list shall also include the cost of completion of each of the outstanding items.
14.3.2 14.1.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 Article 14.1 may, upon request of the Concessionaire to this effect, be issued for operating part of the ProjectAdditional Project Facilities, if at least 90% (ninety percentper cent) of the Additional Project Facilities has been completed. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 1 contract
Sources: Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Project, if at least 90the Concessionaire has completed construction of 100% (ninety percentHundred per cent) of the Project has been completedSite made available to the Concessionaire up to 360 days from the Appointed Date. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 1 contract
Sources: Concession Agreement
Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.
14.3.2 The Parties hereto expressly agree that a Provisional Certificate under this Clause 14.3 may, upon request of the Concessionaire to this effect, be issued for operating part of the Project, if at least 90the Concessionaire has completed construction of 100% (ninety percentHundred per cent) of the Project has been completedSite made available to the Concessionaire up to 146 days from the Appointed Date. Upon issue of such Provisional Certificate, the provisions of Article 15 shall apply to such completed part, and the rights and obligations of the Concessionaire for and in respect of such completed part of the Project shall be construed accordingly.
Appears in 1 contract
Sources: Concession Agreement