Common use of Provisional Certificate Clause in Contracts

Provisional Certificate. 12.2.1 Upon completion of Tests, the Authority Engineer shall satisfy itself that the Tests have been successful and the Project is fit for opening / commissioning. A list of outstandingbut non-critical/non-safety items(called the “Punch List”),duly signed jointly by the Authority Engineer and the

Appears in 6 contracts

Sources: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement

Provisional Certificate. 12.2.1 Upon completion of Tests, the Authority Engineer shall satisfy itself that the Tests have been successful and the Project is fit for opening / commissioning. A list of outstandingbut outstanding but non-critical/non-safety items(called the “Punch List”),duly signed jointly by the Authority Engineer and the

Appears in 1 contract

Sources: Standard Engineering, Procurement and Construction (Epc) Agreement