Common use of Record Drawings and Documentation Clause in Contracts

Record Drawings and Documentation. No later than ninety (90) Days before Final Acceptance of all or part of the Project, Developer shall submit to TxDOT a complete set of Record Drawings in hardcopy and native electronic format for the portion of the Project actually opened to traffic. The Record Drawings and documentation shall be an organized, complete record of Plans and supporting calculations and details that accurately represent what the Developer constructed. Developer shall ensure that the Record Drawings reflect the actual condition of the constructed Work. Developer shall submit to TxDOT the native electronic files used to prepare the Record Drawings and documentation.

Appears in 3 contracts

Sources: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement