Report Content. The System Impact Study report (i) shall address power flow, short circuit, and stability issues identified in the System Impact Study; and (ii) shall provide a description, estimated cost of and schedule for construction of required facilities to interconnect the Generating Facility to Transmission Provider’s Transmission System.