Requests for Information. a. Construction Manager shall submit requests for information using the Project Management Software. b. Architect shall answer requests for information via the Project Management Software. Requests for Information responses that have cost impact will have corresponding Change Order Bulletin (Form SC 6.311) issued by the Architect/ Engineer.
Appears in 6 contracts
Sources: Construction Manager/General Contractor Agreement (Cmgc), Construction Manager/General Contractor Agreement, Construction Manager/General Contractor Agreement
Requests for Information. a. Construction Manager Design/Build Entity shall submit requests for information using the Project Management Software.
b. Architect Architect/Engineer shall answer requests for information via the Project Management Software. Requests for Information responses that have cost impact will have corresponding Change Order Bulletin (Form SC 6.311) issued by the Architect/ Engineer.
Appears in 1 contract
Requests for Information. a. Construction Manager shall submit requests for information using the Project Management Software.
b. Architect Architect/Engineer shall answer requests for information via the Project Management Software. Requests for Information responses that have cost impact will have corresponding Change Order Bulletin (Form SC 6.311SC-6.311) issued by the Architect/ Engineer.
Appears in 1 contract
Requests for Information. a. Construction Manager shall submit requests for information using the Project Management Software.
b. Architect . Architect/Engineer shall answer requests for information via the Project Management Software. Requests for Information responses that have cost impact will have corresponding Change Order Bulletin (Form SC 6.311SC-6.311) issued by the Architect/ Engineer.
Appears in 1 contract