Retainage Amounts Sample Clauses

The Retainage Amounts clause defines the portion of payment that is withheld from a contractor or subcontractor until certain project milestones or completion criteria are met. Typically, a specified percentage of each payment is retained by the project owner to ensure that the contractor completes the work satisfactorily and addresses any deficiencies. This clause applies to construction contracts and helps motivate contractors to finish the project according to the agreed standards. Its core function is to protect the owner's interests by providing leverage to ensure the quality and completion of the work before final payment is released.
POPULAR SAMPLE Copied 1 times
Retainage Amounts. Withhold or cause to be withheld from each Contractor party to a Major Project Document such retainage from any payment to be made to such Contractor as is permitted by such Major Project Document.
Retainage Amounts. Withhold from each Contractor providing labor at the Site (excluding the Parking Structure Contractor), and cause each such Contractor to withhold from its first tier Subcontractors performing labor at the Site, a retainage equal to ten (10%) of each payment made to such Contractor or Subcontractor pursuant to its respective Contract or Subcontract; provided, however, that at such time as (i) the applicable Contractor or Subcontractor shall have completed fifty percent (50%) of the work under its respective Contract or Subcontract and (ii) if a Payment and Performance Bond is required under Section 5.14 with respect to such Contract or Subcontract, the Company shall have obtained a "Consent of Surety to Reduction in or Partial Release of Retainage" (AIA form G707A) from the surety that issued such Payment and Performance Bond and delivered such consent to the Disbursement Agent with a copy to the Construction Consultant, then the retainage withheld may be reduced from ten (10%) percent to five (5%) percent of the contract value as adjusted by change orders, if any.
Retainage Amounts. Withhold from each Contractor performing labor at the Site (excluding the Phase I Parking Structure Contractor and any other Contractor reasonably approved by Disbursement Agent (in consultant with the Construction Consultant)), and cause each such Contractor to withhold from its first tier Subcontractors performing labor at the Site, a retainage equal to ten (10%) of each payment made to such Contractor or Subcontractor pursuant to its respective Contract or Subcontract; provided, however, that at such time as (i) the applicable Contractor or Subcontractor shall have completed fifty percent (50%) of the work under its respective Contract or Subcontract and (ii) if a Payment and Performance Bond is required under Section 5.9 with respect to such Contract or Subcontract, the Company shall have obtained a "Consent of Surety to Reduction in or Partial Release of Retainage" (AIA form G707A) from the surety that issued such Payment and Performance Bond and delivered such consent to the Disbursement Agent with a copy to the Construction Consultant, then the retainage withheld may be reduced from ten (10%) percent to five (5%) percent of the contract value as adjusted by change orders, if any.
Retainage Amounts. The District reserves the right, in its sole discretion, to retain up to 15% of each approved Award payment to assure Contractor’s continued provision of the balance of the Services and compliance with this Agreement. Payment of any retained amounts will be made when the District, in its sole discretion, has determined the Services have been completed in their entirety.
Retainage Amounts. The Borrower shall, and shall cause the Construction Manager (and the EV Contractor, as the case may be) to, withhold as Retainage Amounts from each Contractor Subject to Retainage an amount (a) not less than ten percent (10%) of each payment made to such Contractor Subject to Retainage pursuant to its respective Construction Contract, until such time as the applicable Contractor Subject to Retainage shall have completed fifty percent (50%) of the work under its respective contract; (b) thereafter, not less than five percent (5%) of each payment made to such Contractor Subject to Retainage pursuant to its respective Construction Contract, until such time as the applicable Contractor Subject to Retainage shall have substantially completed all of its work under its respective contract; and (c) thereafter, not less than two and a half percent (2.5%) of each payment made to such Contractor Subject to Retainage pursuant to its respective Construction Contract, until such time as the applicable Contractor Subject to Retainage shall have finally completed all of its work under its respective contract; and (d) not less than one hundred percent (100%) of the amount of defective or incomplete work, as and to the extent permitted pursuant to the terms of the applicable Construction Contract or under applicable law.
Retainage Amounts. The Borrower shall, and shall cause the other Loan Parties and each Contractor to, withhold as Retainage Amounts from each trade Contractor (other than mechanical trades) engaged by such Person in connection with the construction of the Project an amount equal to (i) with respect to each Construction Contract in effect on the Closing Date, the amount of retainage set forth thereunder, and (ii) with respect to each other Construction Contract, not less than ten (10%) of each payment made to such Contractor pursuant to such Construction Contract; provided, however, that at such time as such applicable trade Contractor shall have completed fifty percent (50%) of the work under its respective Construction Contract, the retainage withheld may be reduced from ten (10%) percent to five (5%) percent of the contract value as adjusted by change orders, if any; provided, further, that the Administrative Agent (in consultation with the Construction Consultant) may, at the Borrower’s request, agree to reduce the Retainage Amount for any particular Construction Contract if it determines such reduction to be reasonable under the circumstances; provided, further, that any and all Retainage Amounts under a Construction Contract shall be released within sixty (60) days after final acceptance by the Borrower, the Architect, the Construction Consultant and the Disbursement Agent (acting at the direction of the Administrative Agent) of the work provided under the applicable Construction Contract.
Retainage Amounts. The Borrower shall withhold as Retainage Amounts from each Contractor Subject to Retainage an amount not less than Required Retainage Amounts. Any and all Retainage Amounts under a Construction Contract shall be released within sixty (60) days after final acceptance by the Borrower, the Architect, the Developer and the Disbursement Agent (acting at the direction of the Administrative Agent) of the work provided under the applicable Construction Contract.
Retainage Amounts. Withhold from the Contractor and cause the Contractor to withhold from its Subcontractors performing labor at the site of the Miami Jai-Alai Facility, a retainage equal to ten (10%) of each payment made to the Contractor or Subcontractor pursuant to its respective Construction Document; provided, however, that at such time as (i) the Contractor or the applicable Subcontractor shall have completed fifty percent (50%) of the work under its respective Construction Document and (ii) if a Payment and Performance Bond is required under Section 4.9 with respect to such Construction Document, the Borrower shall have obtained a “Consent of Surety to Reduction in or Partial Release of Retainage” (AIA form G707A) from the surety that issued such Payment and Performance Bond and delivered such consent to the Administrative Agent with a copy to the Construction Consultant, then the retainage withheld may be reduced from ten (10%) percent to five (5%) percent of the contract value as adjusted by change orders, if any.

Related to Retainage Amounts

  • Progress Payments; Retainage A. Owner shall make progress payments on account of the Contract Price on the basis of Contractor’s Applications for Payment on the third Wednesday of the Month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract. 1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract a. 95 percent of Work completed (with the balance being retainage). If the Work has been 50 percent completed as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to Owner and Engineer, there will be no additional retainage; and

  • CP Costs Payments On each Settlement Date, Seller shall pay to Agent (for the benefit of the Conduits) an aggregate amount equal to all accrued and unpaid CP Costs in respect of the outstanding Capital of each of the Conduits for the related Settlement Period in accordance with Article II.

  • FIXED AMOUNTS The fixed amounts contained in Section I of this agreement are based on an estimate of the costs that will be incurred during the period to which the amounts apply. When the actual costs for this period are determined, any differences between the fixed costs used as an estimate and the actual costs will be considered in a subsequent agreement.

  • Monthly Disbursements On or before the fifth (5th) day of each calendar month, during the design and construction of the Tenant Improvements (or such other date as Landlord may designate), Tenant shall deliver to Landlord: (i) a request for reimbursement of amounts paid to the “Contractor,” as that term is defined in Section 4.1.1 of this Tenant Work Letter, approved by Tenant, in a commercially reasonable form to be provided by Landlord, showing the schedule, by trade, of percentage of completion of the Tenant Improvements in the Premises, detailing the portion of the work completed and the portion not completed; (ii) invoices from all of “Tenant’s Agents,” as that term is defined in Section 4.1.2 of this Tenant Work Letter, for labor rendered and materials for the Premises; (iii) executed mechanic’s lien releases, as applicable, from all of Tenant’s Agents which shall comply with the appropriate provisions, as reasonably determined by Landlord, of California Civil Code Section 3262(d); and (iv) all other information reasonably requested by Landlord. Tenant’s request for payment shall be deemed Tenant’s acceptance and approval of the work furnished and/or the materials supplied as set forth in Tenant’s payment request. Within forty-five (45) days thereafter, Landlord shall deliver a check to Tenant made payable to Tenant in payment of the lesser of: (A) the amounts so requested by “tenant as set forth in this Section 2.2.3.1, above (or, subject to the terms of Section 4.2.1, below, a percentage thereof), and (B) the balance of any remaining available portion of the Tenant Improvement Allowance, provided that Landlord does not dispute any request for payment based on non-compliance of any work with the “Approved Working Drawings,” as that term is defined in Section 3.5 below, or due to any substandard work. Landlord’s payment of such amounts shall not be deemed Landlord’s approval or acceptance of the work furnished or materials supplied as set forth in Tenant’s payment request.

  • Interest on Deposit Liabilities The Assuming Institution agrees that, from and after Bank Closing, it will accrue and pay interest on Deposit liabilities assumed pursuant to Section 2.1 at a rate(s) it shall determine; provided, that for non-transaction Deposit liabilities such rate(s) shall not be less than the lowest rate offered by the Assuming Institution to its depositors for non-transaction deposit accounts. The Assuming Institution shall permit each depositor to withdraw, without penalty for early withdrawal, all or any portion of such depositor's Deposit, whether or not the Assuming Institution elects to pay interest in accordance with any deposit agreement formerly existing between the Failed Bank and such depositor; and further provided, that if such Deposit has been pledged to secure an obligation of the depositor or other party, any withdrawal thereof shall be subject to the terms of the agreement governing such pledge. The Assuming Institution shall give notice to such depositors as provided in Section 5.3 of the rate(s) of interest which it has determined to pay and of such withdrawal rights.