Schedule Reports Clause Samples

Schedule Reports. In conjunction with the services provided by Paragraph 3.3.2.1, the CM shall prepare and distribute schedule maintenance reports that shall contrast actual progress against scheduled progress for the Design Phase and the overall Project and shall make recommendations to the Owner for corrective action.
Schedule Reports. 1. Prepare schedule listings of the information in the network diagram in tabular format, sorted according to: a. Early-start, within responsibility. b. Early-start. c. Activity number sequence. d. Activity number sequence with predecessor and successor activity. 2. Schedule listings shall show activity numbers, description, responsibility, total duration in workdays, percent complete, early-start date, late-start date, early-finish date, and total float for each activity in the network diagram. 3. Overall Schedule and subsequent revisions shall reflect actual progress of the project to within 5 working days prior to submittal. The Contractor shall sign and submit three copies of the initial Overall Schedule and each revision. 4. If initial submittal or a subsequent revision does not meet the requirements specified, Contractor shall City of ▇▇▇▇▇▇▇▇, Missouri Water Main Replacement revise the Overall Schedule and resubmit until it is acceptable to the Engineer. Failure to submit and adequately update the Overall Schedule, including network diagram and schedule reports, will be considered cause for withholding partial payments otherwise due under the Contract.
Schedule Reports. PM shall prepare and distribute Schedule Reports during the Pre- Construction and Construction Phase. The Reports shall compare the projected completion dates to scheduled completion dates for the Design Phase, of each separate Contract, and to the Master Schedule for the Project.
Schedule Reports. The Construction Manager shall prepare and distribute biweekly reports that compare actual progress with scheduled progress for the design phases of the Project.
Schedule Reports. The format, filtering, organizing and sorting for each schedule report shall be as directed by the Contracting Officer. Typically reports shall contain: Activity Numbers, Activity Description, Original Duration, Remaining Duration, Early Start Date, Early Finish Date, Late Start Date, Late Finish Date, Total Float, Actual Start Date, Actual Finish Date, and Percent Complete. The following lists typical reports that will be requested. One or all of these reports may be requested for each schedule submission.
Schedule Reports. In conjunction with the services provided herein, the Consultant shall prepare and distribute a Monthly Report that compares actual progress with scheduled progress for the Design Phase and the overall Project and shall make recommendations to the City for corrective action 38074.00001 \31353732 .1
Schedule Reports. HTMI shall timely provide all deliverables, and all progress reports, other reports, documents and information relating to the Services as set forth in the SOW or as Customer may reasonably request. HTMI shall promptly notify Customer of any delay in providing the Services in accordance with the timelines in the applicable SOW, the

Related to Schedule Reports

  • Copies of Reports So long as the Offered Certificates are outstanding, the Depositor shall furnish, or cause to be furnished, to each Underwriter (i) copies of each certification, the annual statements of compliance and the annual independent certified public accountants’ servicing reports furnished to the Certificate Administrator pursuant to the Pooling and Servicing Agreement as soon as practicable after such statements and reports are furnished to the Certificate Administrator; (ii) copies of each amendment to any of the Basic Documents; and (iii) copies of all reports or other communications (financial or other) furnished to holders of the Offered Certificates, and copies of any reports and financial statements furnished to or filed with the Commission, any governmental or regulatory authority or any national securities exchange, all of which may be furnished by the posting thereof on the website of the Certificate Administrator.