Schedule Review. CM will establish the documented procedure for tracking the construction schedule and all updates. It is anticipated that the contractor will provide weekly updates to the schedule during the project progress meetings, however, we also understand there will be a need to participate in stand-alone scheduling meetings. In addition to the weekly update schedules, CM will require the contractor to provide look-ahead schedules in order to ascertain activities that need ▇▇▇▇▇▇▇ County and/or architect/engineer involvement. These procedures will be included in the Project Procedures Manual and will tie closely with the Master Schedule.