Stipulated Sum. A. 1.2.1 The Stipulated Sum shall be « » ($ « » ), subject to authorized adjustments as provided in the Design- Build Documents. 1.2.2 The Stipulated Sum is based upon the following alternates, if any, which are described in the Design-Build Documents and are hereby accepted by the Owner: 1.2.3 Unit prices, if any: Item Units and Limitations Price per Unit ($0.00) § A.1.3 Cost of the Work Plus Design-Builder’s Fee 1.3.1 The Cost of the Work is as defined in Article A.5, Cost of the Work. 1.3.2 The Design-Builder’s Fee:
Appears in 4 contracts
Sources: Design Build Amendment, Design Build Amendment, Design Build Amendment
Stipulated Sum. A.
1.2.1 The Stipulated Sum shall be « «TBD» ($ « » «TBD»), subject to authorized adjustments as provided in the Design- Design-Build Documents.
1.2.2 The Stipulated Sum is based upon the following alternates, if any, which are described in the Design-Build Documents and are hereby accepted by the OwnerManager:
1.2.3 Unit prices, if any: Item Units and Limitations Price per Unit ($0.00) § A.1.3 Cost of the Work Plus Design-Builder’s Fee
1.3.1 The Cost of the Work is as defined in Article A.5, Cost of the Work.
1.3.2 The Design-Builder’s Fee:
Appears in 2 contracts
Sources: Design Build Amendment, Design Build Amendment
Stipulated Sum. A.
1.2.1 The Stipulated Sum shall be « » ($ « » ), subject to authorized adjustments as provided in the Design- Build Documents.
1.2.2 The Stipulated Sum is based upon the following alternates, if any, which are described in the Design-Build Documents and are hereby accepted by the Owner:
1.2.3 Unit prices, if any: Item Units and Limitations Price per Unit ($0.00) § A.1.3 Cost of the Work Plus Design-Builder’s Fee
1.3.1 The Cost of the Work is as defined in Article A.5, Cost of the Work.
1.3.2 The Design-Builder’s Fee:Fee[Intentionally omitted]
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Design Builder
Stipulated Sum. A.
1.2.1 The Stipulated Sum shall be « «TBD» ($ « «TBD» ), subject to authorized adjustments as provided in the Design- Design-Build Documents.
1.2.2 The Stipulated Sum is based upon the following alternates, if any, which are described in the Design-Build describ Documents and are hereby accepted by the OwnerManager:
1.2.3 Unit prices, if any: Item Units and Limitations Price per Unit ($0.00) § A.1.3 Cost of the Work Plus Design-Builder’s Fee
1.3.1 The Cost of the Work is as defined in Article A.5, Cost of the Work.
1.3.2 The Design-Builder’s Fee:
Appears in 1 contract
Sources: Design Build Amendment
Stipulated Sum. A.
1.2.1 The Stipulated Sum shall be « » ($ « » ), subject to authorized adjustments as provided in the Design- Build Documents.
1.2.2 The Stipulated Sum is based upon the following alternates, if any, which are described in the Design-Build Documents and are hereby accepted by the Owner:: « Not applicable »
1.2.3 Unit prices, if any: DRAFT Item Units and Limitations Price per Unit ($0.00) § A.1.3 Cost of the Work Plus Design-Builder’s Fee
1.3.1 The Cost of the Work is as defined in Article A.5, Cost of the Work.
1.3.2 The Design-Builder’s Fee:
Appears in 1 contract
Sources: Design Build Amendment