Stop Work Effective Date. If Contractor has not cured the noticed condition within the 7-day period, or given a valid written reason why Subcontractor’s claim is invalid, then Subcontractor shall have the right to stop work until such noticed conditions are cured. In the case where Contractor orders Subcontractor to stop work the effective date shall be as stated in the order.
Appears in 1 contract
Sources: Subcontract Agreement
Stop Work Effective Date. If Contractor BP has not cured the noticed condition within the 7-day period, or given a valid written reason why Subcontractor’s claim is invalid, then Subcontractor shall have the right to stop work until such noticed conditions are cured. In the case where Contractor BP orders Subcontractor to stop work the effective date shall be as stated in the order.
Appears in 1 contract
Sources: Subcontract Agreement