SUBMITTALS SCHEDULE Sample Clauses

The Submittals Schedule clause defines the requirement for the contractor or supplier to provide a detailed timeline for submitting documents, samples, or other required materials to the project owner or architect. Typically, this schedule outlines when specific submittals—such as shop drawings, product data, or material samples—will be delivered for review and approval throughout the project. By establishing clear deadlines and expectations, this clause helps coordinate project activities, ensures timely review processes, and minimizes delays caused by late or incomplete submissions.
SUBMITTALS SCHEDULE. The Contractor shall submit a detailed listing of all submittals (e.g., mix designs, material certifications) and shop drawings required by the technical specifications. The listing can be developed in a spreadsheet format and shall include:
SUBMITTALS SCHEDULE. Comply with requirements specified in Division 01 Section "Construction Progress Documentation."
SUBMITTALS SCHEDULE. A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, manufacturing, fabrication, and delivery when establishing dates. 1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's Construction Schedule. 2. Submit concurrently with the first complete submittal of Contractor's Construction Schedule.
SUBMITTALS SCHEDULE. Executed Contract.
SUBMITTALS SCHEDULE. Submit six copies of schedule. Arrange the following information in a tabular format: 1. Scheduled date for first submittal. Construction Progress Documentation 01320 - 1 Contract No.: B90644-01H,E 2. Specification Section number and title. 3. Submittal category (action or informational). 4. Name of subcontractor. 5. Description of the Work covered. 6. Scheduled date for Engineer's final release or approval.
SUBMITTALS SCHEDULE. Submit three copies of schedule. Arrange the following information in a tabular format: 1. Scheduled date for first submittal. 2. Specification Section number and title. 3. Submittal category (action or informational). 4. Name of subcontractor. 5. Description of the Work covered. 6. Scheduled date for Architect's final release or approval.
SUBMITTALS SCHEDULE. Submit three (3) copies of schedule. Arrange the following information in a tabular format: G.15.8.9.4.5 Description of the Work covered. G.15.8.9.4.6 Scheduled date for Architect's and Construction Manager's final release or approval.
SUBMITTALS SCHEDULE. ‌ The CMR shall submit a detailed listing of all submittals (for example, mix designs, material certifications) and shop drawings required by the technical specifications. The listing can be developed in a spreadsheet format and shall include: a. Specification item number. b. Item description. c. Description of submittal. d. Specification paragraph requiring submittal. e. Scheduled date of submittal. a. During plant operation for material production, quality control test results and periodic inspections shall be used to ensure the quality of aggregates and other mix components, and to adjust and control mix proportioning to meet the approved mix design and other requirements of the technical specifications. All equipment used in proportioning and mixing shall be inspected to ensure its proper operating condition. The Quality Control Program shall detail how these and other quality control functions will be accomplished and used. b. During field operations, quality control test results and periodic inspections shall be used to ensure the quality of all materials and workmanship. All equipment used in placing, finishing, and compacting shall be inspected to ensure its proper operating condition and to ensure that all such operations are in conformance to the technical specifications and are within the plan dimensions, lines, grades, and tolerances specified. The Program shall document how these and other quality control functions will be accomplished and used.
SUBMITTALS SCHEDULE. A. Revise this Article to suit Project. If there is an office submittal review sequence policy, insert specific requirements. See Evaluations for discussion on submittal review sequence policies.
SUBMITTALS SCHEDULE. Submit two copies of schedule. Arrange the following information in a tabular format: 1. Scheduled date for first submittal. 2. Specification Section number and title. 3. Submittal category (action or informational). 4. Name of subcontractor. 5. Description of the Work covered. 6. Scheduled date for Engineer's final release or approval.