Substantial Completion and Final Completion. 6.2.1 Substantial Completion of the entire Work shall be achieved no later than “To be determined during Phase 1, subject to proposal acceptance and contract amendment.” (TBD) calendar days after the Date of Commencement (“Scheduled Substantial Completion Date”). 6.2.2 Interim milestones and/or Substantial Completion of identified portions of the Work shall be achieved as follows: (Insert any interim milestones (“Scheduled Interim Milestone Dates”) for portions of the Work with different scheduled dates for Substantial Completion.) 6.2.3 Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable. Final Completion is the date when all Work is complete pursuant to the definition of Final Completion set forth in Section 1.2.7 of the General Conditions of Contract. 6.2.4 All of the dates set forth in this Article 6 (“Contract Time(s)”) shall be subject to adjustment in accordance with the General Conditions of Contract.
Appears in 1 contract
Sources: Progressive Design Build Agreement
Substantial Completion and Final Completion. 6.2.1 5.2.1 Substantial Completion of the entire Work shall be achieved no later than “To be determined during Phase 1March 31, subject to proposal acceptance and contract amendment.” (TBD) calendar days 2027 after the Date of Commencement (“Scheduled Substantial Completion Date”).
6.2.2 5.2.2 Interim milestones and/or Substantial Completion of identified portions of the Work shall be achieved as follows: (Insert any interim milestones (“Scheduled Interim Milestone Dates”) may be established as part of a GMP Proposal. The Scheduled Interim Milestone Date for portions N/A shall be achieved no later than (N/A) days after the Date of the Work with different scheduled dates for Substantial CompletionCommencement.)
6.2.3 5.2.3 Final Completion of the Work or identified portions of the Work thereof, and resolution of all unresolved claims shall be achieved as expeditiously as reasonably practicablewithin fourteen (14) days from the Substantial Completion date for the entire Work. Final Completion is the date when all Work is complete pursuant to the definition of Final Completion set forth in Section 1.2.7 of the General Conditions of Contract.
6.2.4 5.2.4 All of the dates set forth in this Article 6 5 (collectively the “Contract Time(s)”) shall be subject to adjustment only in accordance with the General Conditions of Contract.
Appears in 1 contract
Substantial Completion and Final Completion. 6.2.1 Substantial Completion of the entire Work shall be achieved no later than “To be determined during Phase 1August 31, subject to proposal acceptance and contract amendment.” (TBD) calendar days after the Date of Commencement 2025 (“Scheduled Substantial Completion Date”).
6.2.2 Interim milestones and/or Substantial Completion of identified portions of the Work shall be achieved as follows: (Insert any interim milestones (“Scheduled Interim Milestone Dates”) for portions • 60% Design within sixth months of the Work with different scheduled dates date of commencement • 100% Design within two months of Notice to Proceed for Phase II • Substantial Completionproject completion within the earlier of (a) 14 months the Notice to Proceed for Phase 2 or (b) the Scheduled Substantial Completion Date.)
6.2.3 Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable. Final Completion is the date when all Work is complete pursuant to the definition of Final Completion set forth in Section 1.2.7 of the General Conditions of Contract.Contract and as supplemented by Attachment 2 of this Agreement;
6.2.4 All of the dates set forth in this Article 6 (“Contract Time(s)”) shall be subject to adjustment in accordance with the General Conditions of Contract.