Substantial Completion and Final Completion. 5.2.1 Substantial Completion of the entire Work shall be achieved no later than four hundred eighty-five (485) calendar days after the Date of Commencement. However, any delays caused by the modification of Owner’s construction air emission permit as referenced in Section 11, are hereby specifically excluded from the 485 calendar days specified in this section. 5.2.2 Interim milestones and/or Substantial Completion of identified portions of the Work shall be achieved as described in Exhibit F. The Scheduled Substantial Completion date will likewise be extended a corresponding amount of days for each day Owner exceeds the deliverable timeframes referred to in Exhibit F. 5.2.3 Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable, but not later than sixty (60) days following issuance of the Certificate of Substantial Completion. 5.2.4 All of the dates set forth in this Article 5 (“Contract Time(s)”) shall be subject to adjustment in accordance with the General Conditions of Contract. Specifically, if delays in the Contract Time occur because of delay in the delivery of materials or equipment that is beyond the control of Design-Builder, the Contract Time will be adjusted, without penalty to Design-Builder, pursuant to Sections 8.2.1 and 8.2.2 of the General Conditions of Contract.
Appears in 3 contracts
Sources: Design Build Agreement (Heron Lake BioEnergy, LLC), Standard Form of Agreement Between Owner and Design Builder Lump Sum (Heron Lake BioEnergy, LLC), Standard Form of Agreement Between Owner and Design Builder Lump Sum (Heron Lake BioEnergy, LLC)