SUBSTANTIAL COMPLETION AND FINAL PAYMENT. 12.01 The term “substantial completion” as used in the Contract Documents shall mean the first day after the Project Manager has verified that all of the following have been satisfactorily completed: A. All materials and equipment have been incorporated in the Work, including building systems such as, but not limited to, HVAC, Intercom, Fire Alarm, Television, Data, Security System, and the like; B. A certificate of occupancy (Temporary or Final) has been delivered to Project Manager; and C. The Work is completed such that Owner can occupy the entire Project for its intended use, including occupancy by students, without interference from Construction Manager or its Subcontractors.