The 'Substantial Completion date or dates' clause defines the specific point in a construction project when the work is considered sufficiently complete for the owner to use or occupy the building, even if minor tasks remain unfinished. This clause typically outlines the criteria for substantial completion, such as completion of essential systems and obtaining necessary approvals, and may specify different dates for various project phases or sections. Its core practical function is to establish a clear milestone for shifting responsibilities, triggering final payments, and delineating when warranties and risk transfer from the contractor to the owner, thereby reducing ambiguity and potential disputes over project completion.
Substantial Completion date or dates. Date TBD : Calendar days from CMR notice to proceed to substantial completion: 365 Days
Substantial Completion date or dates. « Approximately 180 days after the Notice to Proceed, established upon execution of Agreement between Owner and the Awarded Contractor. »
Substantial Completion date or dates. «See Owner’s RFP attached as Exhibit “E”»
Substantial Completion date or dates. « as provided in the approved Project schedule, provided the Substantial Completion Date shall be sufficient to permit the District to occupy the premises in time for the 2024-2025 school year.»
Substantial Completion date or dates. See Exhibit A, the Project Authorization for the Project.
Substantial Completion date or dates. «The Owner and Architect will develop a milestone schedule or duration to be included in each contract amendment. »
Substantial Completion date or dates. Phase 1: Approximately One (1) week following arrival of generator on site Phase 2: Approximately Twenty (20) weeks from Construction Commencement date
Substantial Completion date or dates. « To be determined in a “Notice to Proceed” to the Contractor. »
Substantial Completion date or dates. To be determined by project packaging and scheduling.