Substantial Completion Delay Liquidated Damages. 5 Owner and Contractor acknowledge and agree that any failure of Contractor to cause Project Substantial Completion to occur by the applicable Guaranteed Substantial Completion Date will directly cause substantial damage to Owner, which damage cannot be ascertained with reasonable certainty. Thus, if such failure occurs, Contractor shall pay to Owner, as liquidated and agreed damages and not as a penalty, the following amount (collectively, “Substantial Completion Liquidated Damages”): $_____ per Day that Project Substantial Completion is delayed beyond the Guaranteed Substantial completion Date.6 Contractor shall not be relieved from the obligation to meet the Guaranteed Substantial Completion Dates except to the extent any such date is extended pursuant to a Change Order or a written notice from Owner.