Substantial Completion Inspections Sample Clauses

Substantial Completion Inspections. Conduct substantial completion inspections when requested by the contractor and the RPR recommends that the work is sufficiently complete to warrant a substantial completion inspection. The following substantial completion inspections are contemplated: ▪ One (1) substantial completion inspection During the substantial completion inspection the inspection staff will prepare initial punch list items requiring completion or correction to the satisfaction of City. The RPR will be responsible for maintaining the punch-list and issuing updates to the punch-list on a periodic basis.

Related to Substantial Completion Inspections

  • Substantial Completion 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which has been accepted in writing to by the State, is substantially complete as defined in Subparagraph

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Project Completion The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch List” corrections and schedule a final project completion job walk. The County will sign the “Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request:

  • Construction Completion The related Construction shall have been completed substantially in accordance with the related Plans and Specifications, the related Deed and all Applicable Laws, and such Leased Property shall be ready for occupancy and operation. All fixtures, equipment and other property contemplated under the Plans and Specifications to be incorporated into or installed in such Leased Property shall have been substantially incorporated or installed, free and clear of all Liens except for Permitted Liens.