Substantial Completion Walk Inspection Sample Clauses

Substantial Completion Walk Inspection. ▇▇▇▇▇▇ will conduct the Substantial Completion Walk required. The construction inspector shall also attend this meeting.
Substantial Completion Walk Inspection conduct the Substantial Completion Walks required before the opening of each phase, (estimated at 2 inspections). The construction inspector shall also attend this meeting.

Related to Substantial Completion Walk Inspection

  • Substantial Completion 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which has been accepted in writing to by the State, is substantially complete as defined in Subparagraph

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Construction Completion The related Construction shall have been completed substantially in accordance with the related Plans and Specifications, the related Deed and all Applicable Laws, and such Leased Property shall be ready for occupancy and operation. All fixtures, equipment and other property contemplated under the Plans and Specifications to be incorporated into or installed in such Leased Property shall have been substantially incorporated or installed, free and clear of all Liens except for Permitted Liens.

  • Project Completion The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch List” corrections and schedule a final project completion job walk. The County will sign the “Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request:

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.