Common use of Substantial Completion Clause in Contracts

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so the Owner can occupy or utilize the Work for its intended use.

Appears in 32 contracts

Sources: Standard Short Form of Agreement Between Owner and Contractor, Standard Short Form of Agreement Between Owner and Contractor, Standard Short Form of Agreement Between Owner and Contractor

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Design-Build Documents so that the Owner can occupy or utilize the Work for its intended use. The date of Substantial Completion is the date certified by the Owner in accordance with this Section 9.8.

Appears in 14 contracts

Sources: Standard Form of Agreement Between Owner and Design Builder, Design Build Agreement, Design Build Construction Agreement

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use.

Appears in 10 contracts

Sources: Master Agreement, Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope, Standard Form of Agreement Between Owner and Contractor

Substantial Completion. Substantial Completion completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so the Owner that District can occupy or utilize the Work for its intended usepurpose.

Appears in 10 contracts

Sources: Flexible Services Contract, Flexible Services Contract, Flexible Services Contract

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the of a Contract Documents so the Owner can occupy or utilize has been completed and installed including completion of commissioning and the Work can be used or occupied for its intended usepurposes, subject only to minor corrections, repairs or modifications.

Appears in 7 contracts

Sources: Dsa Inspection Services Agreement, Architectural Services Agreement, Architectural Services Agreement

Substantial Completion. Substantial Completion is Completion” shall mean the stage in the progress of the Work when or portion of the Work, where the Work or designated portion thereof of the Work is sufficiently complete in accordance with the Contract Documents so the Owner that Customer can occupy or utilize and take beneficial use of the Work for its intended useuse or purpose. A Certificate of Substantial Completion may be executed for an individual subcontract, a specific building, a portion of the Work, or the entire Work.

Appears in 2 contracts

Sources: Energy Services Contract, Energy Services Contract

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents and as certified by the Professional so the Owner can occupy or utilize the Work for its intended use.

Appears in 2 contracts

Sources: Standard Form of Agreement Between Owner and Construction Manager as Constructor, Standard Form of Agreement Between Owner and Construction Manager as Constructor

Substantial Completion. 12.5.1 Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents and where all required occupancy permits, if any, have been issued so the Owner can occupy or utilize the Work for its intended use.

Appears in 1 contract

Sources: Standard Short Form of Agreement Between Owner and Contractor

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work Work, or designated portion thereof thereof, is sufficiently complete in accordance with the Contract Design-Build Documents so the Owner can occupy or utilize the Work for its intended use, which, in this case, is a residential dwelling.

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Design Builder

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use. Substantial Completion shall not be deemed achieved until the Owner’s receipt of certification by the Architect that the Work is Substantially Complete in the form of a Certificate of Substantial Completion.

Appears in 1 contract

Sources: Standard Abbreviated Form of Agreement Between Owner and Contractor

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy enjoy beneficial use or utilize occupancy and may use, operate and maintain the Work project in all respects for its intended usepurpose, all necessary approvals and certificates have been given from the appropriate public regulatory authority, the Owner has received all certificates of occupancy and the Owner has received all required warranties and guaranties and requested documentation.

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Contractor

Substantial Completion. Substantial Completion is means the stage date when the Owner accepts in writing the progress construction of the Work when improvement to real property constituting the Work or any designated portion thereof is sufficiently complete in accordance with the Contract Documents so the Owner can occupy as having reached that state of completion when it may be used or utilize the Work occupied for its intended usepurpose.

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Design Builder

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use., without limitation or interruption, and the Contractor has satisfied the following

Appears in 1 contract

Sources: Master Agreement for Civil Improvements

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended usefacility.

Appears in 1 contract

Sources: Design Build Agreement

Substantial Completion. Substantial Completion completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so the Owner that City can occupy or utilize the Work for its intended usepurpose.

Appears in 1 contract

Sources: Public Improvement Contract

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use. Substantial Completion shall not be dependent on governmental inspection or certificate where the failure to receive a prompt inspection or a certification is caused other than by the fault of the Contractor.

Appears in 1 contract

Sources: Guaranteed Energy Savings Contract Agreement

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so the Owner Manager can occupy or utilize the Work for its intended use.

Appears in 1 contract

Sources: Standard Short Form of Agreement Between Owner and Contractor

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so the Owner Manager can occupy or utilize the Work for its intended use.

Appears in 1 contract

Sources: Standard Short Form of Agreement Between Manager and Contractor

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so the Owner can occupy or utilize the Work for its intended use.is

Appears in 1 contract

Sources: Construction Manager/General Contractor Agreement

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so the Owner LOCCC can occupy or utilize the Work for its intended use.

Appears in 1 contract

Sources: Standard Short Form of Agreement Between Owner and Contractor

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use. Notwithstanding anything in the Contract Documents to the contrary, this shall include, but is not limited to, start up and successful testing of all systems and equipment.

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Construction Manager as Constructor

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so the Owner can occupy or utilize the Work for its intended use.

Appears in 1 contract

Sources: Standard Short Form of Agreement Between Owner and Contractor

Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents Documents, so the Owner can occupy or utilize the Work for its intended use.

Appears in 1 contract

Sources: Construction Contract

Substantial Completion. Substantial Completion defined: Substantial Completion is the stage in the progress of the Work (or portion thereof designated and approved by Owner) when the Work or designated portion thereof construction is sufficiently complete complete, in accordance with the Contract Documents Documents, so Owner has full and unrestricted use and benefit of the Owner can occupy facilities (or utilize portion thereof designated and approved by Owner) for the Work for its intended use.use for

Appears in 1 contract

Sources: General Conditions Contract