Substantial Completion. § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work: § 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date § 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.
Appears in 32 contracts
Sources: Construction Contract, Construction Contract, Standard Form of Agreement Between Owner and Contractor Where the Basis of Payment Is a Stipulated Sum
Substantial Completion. § 3.3.1 A.
2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor Construction Manager shall achieve Substantial Completion of the entire Work:
§ 3.3.2 2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor Construction Manager shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 2.3.3 If the Contractor Construction Manager fails to achieve Substantial Completion as provided in this Section 3.3A.2.3, liquidated damages, if any, shall be assessed as set forth in Section 4.56.1.6 of the Agreement.
Appears in 8 contracts
Sources: Construction Manager/General Contractor Agreement, Guaranteed Maximum Price Amendment, Guaranteed Maximum Price Amendment
Substantial Completion. § 3.3.1 4.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 4.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 4.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.34.3, liquidated damages, if any, shall be assessed as set forth in Section 4.55.1.6.
Appears in 5 contracts
Sources: Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Contractor
Substantial Completion. § 3.3.1 A.
2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor Construction Manager shall achieve Substantial Completion of the entire Work:: « »
§ 3.3.2 2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor Construction Manager shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 2.3.3 If the Contractor Construction Manager fails to achieve Substantial Completion as provided in this Section 3.3A.2.3, liquidated damages, if any, shall be assessed as set forth in Section 4.56.1.6 of the Agreement.
Appears in 4 contracts
Sources: Guaranteed Maximum Price Amendment, Guaranteed Maximum Price Amendment, Standard Form of Agreement Between Owner and Construction Manager as Constructor
Substantial Completion. § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date:
§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.
Appears in 4 contracts
Sources: Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Contractor
Substantial Completion. § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:: NOT FOR BIDDING
§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
Date § 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.
Appears in 3 contracts
Sources: Facilities and Special Projects Contract, Facilities and Special Projects Contract, Roof Replacement Contract
Substantial Completion. § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
Date § 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.
Appears in 3 contracts
Sources: Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Contractor, Standard Form of Agreement Between Owner and Contractor
Substantial Completion. § 3.3.1 2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 2.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.32.3, liquidated damages, if any, shall be assessed as set forth in Section 4.53.5.
Appears in 2 contracts
Sources: Standard Abbreviated Form of Agreement Between Owner and Contractor, Standard Abbreviated Form of Agreement Between Owner and Contractor
Substantial Completion. § 3.3.1 A.
2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor Construction Manager shall achieve Substantial Completion of the entire Work:: « » « »
§ 3.3.2 2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor Construction Manager shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 2.3.3 If the Contractor Construction Manager fails to achieve Substantial Completion as provided in this Section 3.3A.2.3, liquidated damages, if any, shall be assessed as set forth in Section 4.56.1.6 of the Agreement.
Appears in 2 contracts
Sources: Guaranteed Maximum Price Amendment, Guaranteed Maximum Price Amendment
Substantial Completion. § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.33.3 , liquidated damages, if any, shall be assessed as set forth in Section 4.5.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor
Substantial Completion. § 3.3.1 4.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 4.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date:
§ 3.3.3 4.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.34.3, liquidated damages, if any, damages shall be assessed as set forth in Section 4.55.1.6.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor
Substantial Completion. § 3.3.1 A.
2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor Construction Manager shall achieve Substantial Completion of the entire Work:: « »
§ 3.3.2 2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor Construction Manager shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
Date § 3.3.3 A.2.3.3 If the Contractor Construction Manager fails to achieve Substantial Completion as provided in this Section 3.3A.2.3, liquidated damages, if any, shall be assessed as set forth in Section 4.56.1.6 of the Agreement.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Construction Manager as Constructor
Substantial Completion. § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.
Appears in 1 contract
Sources: Aia Document A101tm – 2017
Substantial Completion. § 3.3.1 A.
2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor Construction Manager shall achieve Substantial Completion of the entire Work:: « » X
§ 3.3.2 2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor Construction Manager shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 2.3.3 If the Contractor Construction Manager fails to achieve Substantial Completion as provided in this Section 3.3A.2.3, liquidated damages, if any, shall be assessed as set forth in Section 4.56.1.6 of the Agreement.
Appears in 1 contract
Sources: Guaranteed Maximum Price Amendment
Substantial Completion. § 3.3.1 4.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 4.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion DateDate [List Phased Milestones]
§ 3.3.3 4.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.34.3, liquidated damages, if any, damages shall be assessed as set forth in Section 4.55.1.6.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor
Substantial Completion. [CLT1]
§ 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor
Substantial Completion. § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work i are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial a Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor
Substantial Completion. § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall diligently prosecute and achieve Substantial Completion of the entire Work:
§ 3.3.2 Subject If applicable, subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.54.5 below.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor
Substantial Completion. § 3.3.1 2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion DateNot Applicable.
§ 3.3.3 2.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.32.3, liquidated damages, if any, shall be assessed as set forth in Section 4.53.5.
Appears in 1 contract
Sources: Standard Abbreviated Form of Agreement Between Owner and Contractor
Substantial Completion. § 3.3.1 2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 2.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.32.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.3.5. Not Applicable
Appears in 1 contract
Sources: Standard Abbreviated Form of Agreement Between Owner and Contractor
Substantial Completion. § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date
§ 3.3.3 If the Contractor fails to achieve Substantial Completion of the entire Work or portions of the Work as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor