Subsurface Utility Exploration (▇▇▇) Sample Clauses

Subsurface Utility Exploration (▇▇▇). If needed, ▇▇▇ will be initiated after the alignment is approved by the City. FNI will retain an ▇▇▇ firm as a subconsultant to perform tasks outlined in the supplemental services Item K. ▇▇▇ will not proceed unless approved by the City.

Related to Subsurface Utility Exploration (▇▇▇)

  • Underground Utilities Any required ground digging or subsurface work shall be done in accordance with Chapter 556, Florida Statutes. It shall be the responsibility of CONTRACTOR to have all underground utilities located before any work begins (Sunshine State One Call ▇-▇▇▇-▇▇▇-▇▇▇▇). The repairs of any damaged underground utilities as a result of the work being performed by CONTRACTOR shall be the responsibility of CONTRACTOR. The proper utility company shall be contacted immediately to expedite the repairs, if damage has occurred. CONTRACTOR will notify the COUNTY and provide a written explanation of the incident within two (2) days of the damage to any underground utilities.

  • Subsurface Conditions Unless the Contract Documents stipulate specific quantities and units of rock or unsuitable soils, the Contractor shall assume material below the surface of the Earth to be earth and other material that can be removed by power shovel or similar equipment. Should conditions encountered below the surface of the ground be at variance to the number of unit requirements as indicated by drawings or specifications, and absent an agreed-upon unit price established prior to the bid by Addendum, or after contract execution by Change Order, the Contract Sum and/or time shall be adjusted as provided in the Contract Documents for changes in the work.

  • Alpine Areas As of 1 March 2024, the Employer shall pay an Alpine disability allowance of $4.45 for hours worked on Projects in alpine areas. These allowances will be adjusted annually in accordance with CPI (All Groups, Melbourne) movements measured in the twelve month period ending the previous December quarter effective as of 1 March 2025, rounded to the nearest 5 cents.

  • Underground Tanks If underground or other storage tanks storing Hazardous Materials located on the Premises or the Project are used by Tenant or are hereafter placed on the Premises or the Project by Tenant, Tenant shall install, use, monitor, operate, maintain, upgrade and manage such storage tanks, maintain appropriate records, obtain and maintain appropriate insurance, implement reporting procedures, properly close any underground storage tanks, and take or cause to be taken all other actions necessary or required under applicable state and federal Legal Requirements, as such now exists or may hereafter be adopted or amended in connection with the installation, use, maintenance, management, operation, upgrading and closure of such storage tanks.

  • Underground Facilities All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including without limitation those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.