The 'Such Certificate of Substantial Completion' clause formally recognizes that a significant portion of the contracted work has been finished to a level where it can be used for its intended purpose, even if minor tasks remain. Typically, this certificate is issued by an architect or project manager after inspection, and it may trigger important contractual events such as the start of warranty periods or the release of certain payments. Its core function is to provide a clear, documented milestone in the project, reducing ambiguity about when substantial completion is achieved and helping to manage responsibilities and risk between the parties.
Such Certificate of Substantial Completion for a part of the Works shall not relieve the Contractor of his responsibilities under the Contract, and the Contractor shall be deemed to have undertaken to complete with due expedition any outstanding work and rectification of defects in that part of the Works during the Defects Liability Period as provided in Article 27 of this Contract. A separate Defects Liability Period shall apply for each separate section or separable part taken over in accordance with the above

Related to Such Certificate of Substantial Completion

  • Certificate of Substantial Completion The certificate prepared by the Designer and approved by the Owner to the effect that the Work has reached Substantial Completion.

  • Certificate of Completion The Interconnection Customer shall provide the EDC with a completed copy of the Interconnection Agreement Certificate of Completion, including evidence of the electrical inspection performed by the local authority having jurisdiction. The evidence of completion of the electrical inspection may be provided on inspection forms used by local inspecting authorities. The Interconnection request shall not be finally approved until the EDC’s representative signs the Interconnection Agreement Certificate of Completion.

  • Substantial Completion 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which has been accepted in writing to by the State, is substantially complete as defined in Subparagraph

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.