Survey control and setting out of the works. The positions of the foundation bases will be set out using the drawings and existing equipment within the yard by the Contractor and checked by the SS before excavation work can commence. This is a Hold & witness point.

Appears in 2 contracts

Sources: Nec3 Engineering and Construction Short Contract, Nec3 Engineering and Construction Short Contract