Temporary Works Sample Clauses
The Temporary Works clause defines the responsibilities and requirements related to the design, installation, maintenance, and removal of temporary structures or systems needed during construction. This clause typically applies to items such as scaffolding, formwork, shoring, or access platforms that are not part of the finished project but are essential for safe and efficient construction activities. By clearly assigning responsibility and setting standards for temporary works, the clause helps ensure safety, compliance with regulations, and smooth project progress, while minimizing risks associated with temporary structures.
POPULAR SAMPLE Copied 12 times
Temporary Works. 5.9.1 All temporary works necessary for the proper execution of the Project shall be provided and maintained by the Developer and subject to the consent of the Nodal Officer shall be removed by it when they are no longer required and in such manner as the Nodal Officer shall direct. If temporary works or storage or accommodation are provided by the Developer on the Project Land or any other land permitted by the Nodal Officer (including any Railway land), for the Project for any labour engaged by him for the execution of Project and after obtaining the written consent of the owner of such land, the Developer shall arrange for handing over vacant possession of the said land after relevant works/ use so permitted is completed.
Temporary Works. The Contractor shall carry out at his expense all the Temporary Works to enable the Works to be carried out. He shall submit to the Engineer drawings of Temporary Works, which he intends to use, such as cofferdams, scaffolding, trusses and shuttering. He shall take account of any observations made to him by the Engineer, while remaining responsible for these drawings.
Temporary Works. The Contractor shall obtain written permission from the Employer’s Agent before construction of any temporary works may commence. Temporary works will include the following:
(a) Where applicable (in limited occupation areas), transverse and longitudinal ramps at the end of each shift during construction of the asphalt overlays on the runways and taxiways. The details for the construction and removal of these ramps are discussed in the project specification.
(b) Signage and markings for the surface movement of aircraft and vehicles.
(c) Placing and removal of barricades where required.
(d) All facilities within the Contractor’s construction camp. The design shall comply with the specifications, where provided in these documents and all statutory requirements such as the Occupational Health and Safety Act and Regulations. The area is to be reinstated upon completion.
(e) Access roads for the construction camp and temporary material stockpile site. These roads are to be designed, constructed and maintained by the Contractor to comply with safety and environmental requirements. They must be reinstated upon completion of the Works.
Temporary Works. Add the following to this clause:
Temporary Works. (a) The Participants must carry out all Temporary Works required to execute the Alliance Activities so that the Alliance Works are fit for their intended purposes.
(b) Where any Temporary Works are to be carried out on any property, the Participants must give written notice to the Principal's Representative identifying such property and describing the Temporary Works to be performed on such property. Such notice must:
(i) be given prior to the date on which the Participants intend to commence the Temporary Works; and
(ii) specify the intended commencement and completion dates.
(c) The Participants must keep a register of all notices under clause 8.8(b) and make this register available to the Principal's Representative and TPD's Property Group for inspection and copying at all reasonable times.
(d) Upon being given access to any property for the purpose of carrying out any Temporary Works, the Participants must promptly carry out those Temporary Works in a manner which:
(i) minimises inconvenience and disruption to the owners, occupiers and users of the property; and
(ii) complies with the requirements set out in the TSRs.
(e) The Participants must:
(i) reinstate any property upon which any Temporary Works have been carried out to a state that is equivalent to the state it was in immediately prior to the Participants obtaining access; and
(ii) otherwise repair any damage or degradation to any part of any property arising out of or in any way in connection with the performance of its obligations under this clause 8.8.
(f) The completion of all Temporary Works under this clause 8.8 is a condition precedent to Completion of the Alliance Works or any Portion.
Temporary Works. The Contractor must obtain written permission from the Engineer before construction of any temporary works may commence. Temporary works will include the following:
(a) Signage and markings for the surface movement of aircraft and vehicles
(b) Electrical connections to maintain circuits for the safe operation of elements.
(c) Placing and removal of barricades.
(d) All facilities within the Contractor’s construction camp. The site is to be negotiated with ACSA and shall be fenced off using 2,0 m high diamond mesh fencing material. The design shall comply with the specifications where, provided in these documents and all statutory requirements such as the Occupational Health and Safety Act and Regulations. The area is to be reinstated upon completion.
(e) Temporary backfilling of excavations (at the end of each work shift) within the safety zone next to the runway and taxiways. The backfilling must comply with ICAO requirements.
(f) Temporary backfilling of excavations (at the end of each work shift) within the safety zone next to the taxiways. The backfilling must comply with ICAO requirements.
Temporary Works. The CIDS/ODS Contractor must carry out all Temporary Works required to execute the CIDS/ODS Contractor's Activities so that the Temporary Works will be fit for their intended purpose.
Temporary Works. There are no specific temporary works required to be undertaken by the Contractor apart from the works specified on the scope. The Contractor is however required to undertake all Temporary Works necessary to keep the existing services fully operational and to keep down time to a minimum, until the new services have been installed and tested, where after the existing services are to be decommissioned and made safe, and the new services commissioned.
Temporary Works. All temporary works necessary for the proper execution of the works shall be provided and maintained by the Contractor and subject to the consent of the Engineer shall be removed by him at his expenses when they are no longer required and in such manner as the Engineer shall direct. In the event of failure on the part of the Contractor to remove the temporary works, the Engineer will cause them to be removed and cost as increased by supervision and other incidental charges shall be recovered from the Contractor. If temporary huts are provided by the Contractor on the Railway land for labour engaged by him for the execution of works, the Contractor shall arrange for handing over vacant possession of the said land after the work is completed; if the Contractor's labour refuse to vacate, and have to be evicted by the Railway, necessary expenses incurred by the Railway in connection therewith shall be borne by the Contractor.
Temporary Works. 4.1 General clauses
4.2 Location of temporary works and Museum Objects
4.3 Temporary lighting and power for the works
4.4 Temporary accessways and roads
4.5 4.8 Temporary fencing, hoarding, gantries and shoring 4.9-4.11 Operation of mechanical plant 5.1-5.4 Handover procedures 5.5 Financial information at Practical Completion 5.6 Health and Safety File 5.7 Keys 5.8 Fire Officer