Temporary Works. (a) The Participants must carry out all Temporary Works required to execute the Alliance Activities so that the Alliance Works are fit for their intended purposes. (b) Where any Temporary Works are to be carried out on any property, the Participants must give written notice to the Principal's Representative identifying such property and describing the Temporary Works to be performed on such property. Such notice must: (i) be given prior to the date on which the Participants intend to commence the Temporary Works; and (ii) specify the intended commencement and completion dates. (c) The Participants must keep a register of all notices under clause 8.8(b) and make this register available to the Principal's Representative and TPD's Property Group for inspection and copying at all reasonable times. (d) Upon being given access to any property for the purpose of carrying out any Temporary Works, the Participants must promptly carry out those Temporary Works in a manner which: (i) minimises inconvenience and disruption to the owners, occupiers and users of the property; and (ii) complies with the requirements set out in the TSRs. (e) The Participants must: (i) reinstate any property upon which any Temporary Works have been carried out to a state that is equivalent to the state it was in immediately prior to the Participants obtaining access; and (ii) otherwise repair any damage or degradation to any part of any property arising out of or in any way in connection with the performance of its obligations under this clause 8.8. (f) The completion of all Temporary Works under this clause 8.8 is a condition precedent to Completion of the Alliance Works or any Portion.
Appears in 1 contract
Sources: Project Alliance Agreement
Temporary Works. (a) The Participants must carry out all Temporary Works required to execute the Alliance Activities so that the Alliance Works are fit for their intended purposespurposes as stated in, or reasonably inferred from, the Works Brief and this Agreement.
(b) Where any Temporary Works are to be carried out on any property, the Participants must give written notice to the Principal's Representative identifying such property and describing the Temporary Works to be performed on such property. Such notice must:
(i) be given prior to the date on which the Participants intend to commence the Temporary Works; and
(ii) specify the intended commencement and completion dates.
(c) The Participants must keep a register of all notices under clause 8.8(b) and make this register available to the Principal's Representative and TPD's Property Group for inspection and copying at all reasonable times.
(d) Upon being given access to any property for the purpose of carrying out any Temporary Works, the Participants must promptly carry out those Temporary Works in a manner which:
(i) minimises inconvenience and disruption to the owners, occupiers and users of the property; and
(ii) complies with the requirements set out in the TSRs.
(e) The Participants must:
(i) reinstate any property upon which any Temporary Works have been carried out to a state that is equivalent to the state it was in immediately prior to the Participants obtaining access; and
(ii) otherwise repair any damage or degradation to any part of any property arising out of or in any way in connection with the performance of its obligations under this clause 8.8.
(f) The completion of all Temporary Works under this clause 8.8 is a condition precedent to Completion of the Alliance Works or any Portion.
Appears in 1 contract
Sources: Project Alliance Agreement