Common use of Synchronization, Commissioning and Commercial Operation Clause in Contracts

Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and SECI and also Buying Entity at least sixty (60) days’ advanced preliminary written notice and at least thirty (30) days’ advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.

Appears in 4 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and SECI and also Buying Entity NVVN at least sixty (60) days’ days advanced preliminary written notice and at least thirty (30) days’ days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.

Appears in 3 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and SECI and also Buying Entity Buyer at least sixty (60) days’ advanced preliminary written notice and at least thirty (30) days’ advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.

Appears in 2 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/RLDC/ SLDC and SECI and also Buying Entity Buyer at least sixty (60) days’ advanced preliminary written notice and at least thirty (30) days’ advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.

Appears in 2 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and SLDC, SECI and also Buying Entity ▇▇▇▇ (if applicable) at least sixty twenty (6020) days’ days advanced preliminary written notice and at least thirty ten (301) days’ days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.

Appears in 1 contract

Sources: Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and SECI and also Buying Entity at least sixty (60) days’ days advanced preliminary written notice and at least thirty (30) days’ days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.

Appears in 1 contract

Sources: Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and SLDC, SECI and also Buying Entity Solar Park Implementing Agency (if applicable) at least sixty (60) days’ days advanced preliminary written notice and at least thirty (30) days’ days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.

Appears in 1 contract

Sources: Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and SECI and also Buying Entity at least sixty (60) days’ days advanced preliminary written notice and at least thirty (30) days’ days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.

Appears in 1 contract

Sources: Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and SLDC, SECI and also Buying Entity OFC, KANPUR (if applicable) at least sixty twenty (6020) days’ days advanced preliminary written notice and at least thirty ten (301) days’ days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.

Appears in 1 contract

Sources: Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and SECI and also Buying Entity DVC at least sixty (60) days’ advanced preliminary written notice and at least thirty (30) days’ advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System.

Appears in 1 contract

Sources: Power Purchase Agreement