Synchronisation Commissioning and Commercial Operation Sample Clauses
POPULAR SAMPLE Copied 1 times
Synchronisation Commissioning and Commercial Operation. 8.1 The Solar Power Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 Subject to Clause 8.1, the Power Project shall be synchronized by the Solar Power Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 The synchronization equipment shall be installed by the Solar Power Developer at its generation facility of the Power Project at its own cost. The Solar Power Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 The Solar Power Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code.
8.5 The Solar Power Developer shall commission the Project within 10 (ten)20 months from the Effective Date as per PPA. 20 Addendum-1 dated 22.02.2018 of Re-called tender
Synchronisation Commissioning and Commercial Operation. 8.1 The Developer shall provide at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code.
8.5 The Developer shall commission the Project within 12 (twelve)/24 (twenty four)13 months from the Effective Date.
Synchronisation Commissioning and Commercial Operation. 5.1.1 The SPP shall give the concerned UPLDC / SLDC and Procurer and UPNEDA at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice, of the date on which it intends to synchronise the Power Project to the Grid System.
Synchronisation Commissioning and Commercial Operation. Synchronisation, Commissioning and Commercial Operation The SPD shall give the concerned SLDC and MePDCL at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System. Subject to Article 5.1.1, the Power Project may be synchronized by the SPD to the Grid System when it meets all the connection conditions prescribed in Meghalaya Grid Code then in effect and otherwise meets all other Indian/ State legal requirements for synchronization to the Grid System. The synchronization equipment shall be installed by the SPD at its generation facility of the Power Project at its own cost. The SPD shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/ Grid System of MePDCL and checking/ verification is made by the concerned Transco and Discoms Authorities of the Grid System. The SPD shall immediately after each synchronization /tripping of generator, inform the sub- station of the Grid System to which the Power Project is electrically connected in accordance with State Grid Code. The SPD shall commission the project within 15 months for MW power plant.
Synchronisation Commissioning and Commercial Operation. 5.1 Synchronization, Commissioning and Commercial Operation
5.1.1 The REPD shall give NDMC at least sixty (60) Days advanced preliminary written notice and at least thirty (30) Days advanced final written notice, of the date on which it intends to synchronize the Power Project to the grid system.
Synchronisation Commissioning and Commercial Operation. 5.1.1 The SPD shall give the concerned RLDC/SLDC and NVVN at least sixty (60) days advanced preliminary written notice and atleast thirty (30) days advanced final written notice, of the date on which it intends to synchronise the Power Project to the Grid System.
5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the SPD to the Grid System when it meets all the connection conditions prescribed in any Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
5.1.3 The synchronization equipment shall be installed by the SPD at its generation facility of the Power Project at its own cost. The SPD shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the Chief Engineer of the concerned sub-station/Grid System and checking/verification is made by the concerned Senior Executive Enggr. (Protection) of the Grid System.
Synchronisation Commissioning and Commercial Operation.
8.1. The Developer shall provide at least Thirty (30) days advanced preliminary written notice and at least fifteen (15) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2. Subject to Clause 8.1, the Power Project shall be synchronized by the Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3. The synchronization equipment shall be installed by the Developer at its generation facility of the Power Project at its own cost. The Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4. The Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. In addition, the developer RPG will inject in-firm power to grid time to time to carry out operational/ functional test prior to commercial operation. For avoidance of doubt, it is clarified that Synchronization / Connectivity of the Project with the grid shall not to be considered as Commissioning of the Project
8.5. The Developer shall commission the Project within 18 (Eighteen ) months from the Effective Date of this PPA.
Synchronisation Commissioning and Commercial Operation. 8.1 The SPG shall provide at least thirty (30) days advance preliminary written notice and at least fifteen (15) days advance final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.
8.2 Subject to Article 8.1, the Power Project shall be synchronized by the SPG with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
8.3 The synchronization equipment and all necessary arrangements/equipments including RTU for scheduling of power generated from the project and transmission of data to the concerned authority as per applicable regulations shall be installed by the SPG at its generation facility of the Power Project at its own cost. The SPG shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System.
8.4 The SPG shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. In addition, the SPG will inject infirm power to grid time to time to carry out operational/functional test prior to commercial operation. For avoidance of doubt, it is clarified that Synchronization/Connectivity of the Project, during operational/functional test, with the grid shall not to be considered as Commissioning of the Project.
8.5 The SPG shall commission the Project within SCOD/COD and supply power to the ESCOM grid as prescibed under Article 5.8.3 of this PPA.
8.6 In case, the SPG commission the plant within three (3) months from the SCOD, the SPG shall pay ESCOM as penalty for such delay in commencement of supply of power as prescibed under Article 5.8.1 of this PPA.
8.7 In case, the SPG commission the plant beyond three (3) months and within four (4) months from SCOD, Article 5.8.2 of this PPA will be applicable.
8.8 In case, the SPG fails to commission the plant within four (4) months from SCOD, Article
Synchronisation Commissioning and Commercial Operation. The SHPD shall give SLDC and GRIDCO at least sixty (60) days’ advanced preliminary written notice and at least thirty (30) days’ advanced final written notice of the date on which it intends to synchronize the Project to the Grid System. The Project may be synchronized by the SHPD to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. The synchronization equipment and all necessary arrangements / equipments including RTU for transmission of data to the concerned authority as per applicable regulations shall be installed by the SHPD at its generation facility at its own cost. The SHPD shall synchronize its system with the Grid System only after the approval of synchronization scheme by the head of the concerned substation/Grid System and checking/verification is made by the concerned authorities of the Grid System. The SHPD shall immediately after each synchronization/tripping of generator, inform SLDC and the sub-station of the Grid System to which the station is electrically connected in accordance with applicable Grid Code under intimation to GRIDCO. In addition, the SHPD will draw start-up/construction power and inject in-firm power from/to grid time to time to carry out operational/ functional test prior to commercial operation. For avoidance of doubt, it is clarified that Synchronization / Connectivity of the station with the grid shall not to be considered as Commissioning of the station. For drawl of Start-up/Construction power from the grid, the SHPD shall be the consumer of the concerned DISCOM and pay applicable tariff to the DISCOM.
Synchronisation Commissioning and Commercial Operation