Common use of Synchronization, Commissioning and Commercial Operation Clause in Contracts

Synchronization, Commissioning and Commercial Operation. 8.1 The Solar Power Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to APDCL of the date on which it intends to synchronize the Power Project to the Grid System. 8.2 Subject to Clause 8.1, the Power Project shall be synchronized by the Solar Power Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System 8.3 The synchronization equipment shall be installed by the Solar Power Developer at its generation facility of the Power Project at its own cost. The Solar Power Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub- station/Grid System and checking/verification is made by the concerned authorities of the Grid System 8.4 The Solar Power Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code 8.5 The Solar Power Developer shall commission the Project within 18 (eighteen) months from the Effective Date as per PPA

Appears in 11 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 8.1 The Solar Power Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to APDCL of the date on which it intends to synchronize the Power Project to the Grid System. 8.2 Subject to Clause 8.1, the Power Project shall be synchronized by the Solar Power Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System 8.3 The synchronization equipment shall be installed by the Solar Power Developer at its generation facility of the Power Project at its own cost. The Solar Power Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub- sub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System 8.4 The Solar Power Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code 8.5 The Solar Power Developer shall commission the Project within 18 12 (eighteentwelve) months from the Effective Date as per PPA

Appears in 2 contracts

Sources: Power Purchase Agreement, Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 8.1 3.10.1 The Solar Power Developer shall provide give the concerned SLDC and DISCOM at least forty sixty (4060) days advanced advance of preliminary written notice and at least twenty thirty (2030) days advanced advance of final written notice to APDCL notice, of the date on which it intends to synchronize the Power Project to the Grid Systemgrid system. 8.2 Subject to Clause 8.1, the Power 3.10.2 The Project shall may be synchronized by the Solar Power Developer with to the Grid System grid system when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid Systemgrid system. 8.3 3.10.3 The synchronization equipment shall be installed by the Solar Power Developer at its generation facility of the Power Project at its own cost. The Solar Power Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub- sub-station/Grid System grid system and checking/verification is made by the concerned authorities of the Grid Systemgrid system. 8.4 3.10.4 The Solar Power Developer shall immediately after each synchronization/synchronization/ tripping of generator, inform the sub-station of the Grid System grid system to which the Power Project is electrically connected in accordance with applicable Grid Code. 8.5 3.10.5 The Solar Power Developer shall commission the Project within 18 twelve (eighteen12) months from Months of the Effective Date as per PPAdate of signing of this Agreement, and delayed commissioning of the same is subject to the penalties and incentives stated in Clause 10.5 and Clause 3.11.

Appears in 1 contract

Sources: Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 8.1 The Solar Power Developer shall provide at least forty twenty (4020) days advanced preliminary written notice and at least twenty ten (2010) days advanced final written notice to APDCL of the date on which it intends to synchronize the Power Project to the Grid System. 8.2 Subject to Clause 8.1, the Power Project shall be synchronized by the Solar Power Developer with the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System 8.3 The synchronization equipment shall be installed by the Solar Power Developer at its generation facility of the Power Project at its own cost. The Solar Power Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub- station/Grid System and checking/verification is made by the concerned authorities of the Grid System 8.4 The Solar Power Developer shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code 8.5 The Solar Power Developer shall commission the Project within 18 (eighteen) months from the Effective Date as per PPAon or before 31.07.2024.

Appears in 1 contract

Sources: Engineering, Procurement & Construction Agreement