Synchronization, Commissioning and Commercial Operation. 3.9.1 The WtE Developer shall give a written notice to the concerned SLDC and DISCOM, at least sixty (60) days in advance to the date on which it intends to synchronize the Project to the grid system. 3.9.2 The Project may be synchronized by the WtE Developer to the grid system when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the grid system. 3.9.3 The synchronization equipment shall be installed by the WtE Developer at its generation facility of the Project at its own cost. The WtE Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/grid system and checking/verification is made by the concerned authorities of the grid system. 3.9.4 The WtE Developer shall immediately after synchronization/ tripping of generator, inform the sub-station of the grid system to which the Project is electrically connected in accordance with applicable Grid Code as amended from time to time. 3.9.5 The WtE Developer shall commission the Project within timelines defined for Scheduled COD as per this Agreement, and any delay of the same is subject to the penalties stated in Clause 10.5 of this Agreement.
Appears in 3 contracts
Sources: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Synchronization, Commissioning and Commercial Operation.
3.9.1 3.10.1 The WtE Developer shall give a written notice to the concerned SLDC and DISCOM, at least sixty (60) days in advance to the date on which it intends to synchronize the Project to the grid system.
3.9.2 3.10.2 The Project may be synchronized by the WtE Developer to the grid system when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the grid system.
3.9.3 3.10.3 The synchronization equipment shall be installed by the WtE Developer at its generation facility of the Project at its own cost. The WtE Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/grid system and checking/verification is made by the concerned authorities of the grid system.
3.9.4 3.10.4 The WtE Developer shall immediately after synchronization/ tripping of generator, inform the sub-station of the grid system to which the Project is electrically connected in accordance with applicable Grid Code as amended from time to time.
3.9.5 3.10.5 The WtE Developer shall commission the Project within timelines defined for Scheduled COD as per this Agreement, and any delay of the same is subject to the penalties stated in Clause 10.5 of this Agreement.
Appears in 2 contracts
Synchronization, Commissioning and Commercial Operation.
3.9.1 Officials from APDISCOMs & APTRANSCO shall undertake inspection of project for declaration of COD. The WtE Developer shall give a written notice to the concerned SLDC and DISCOM, at least sixty (60) days in advance to the date on which it intends to synchronize the Project to the grid system.
3.9.2 The Project may be synchronized by the WtE Developer to the grid system when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the grid system.
3.9.3 The synchronization equipment shall be installed by the WtE Developer at its generation facility of the Project at its own cost. The WtE Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/grid system and checking/verification is made by the concerned authorities of the grid system.
3.9.4 The WtE Developer shall immediately after synchronization/ tripping of generator, inform the sub-station of the grid system to which the Project is electrically connected in accordance with applicable Grid Code as amended from time to time.
3.9.5 The WtE Developer shall commission the Project within timelines defined for Scheduled COD as per this Agreement, and any delay of the same is subject to the penalties stated in Clause 10.5 of this Agreement.
Appears in 2 contracts
Synchronization, Commissioning and Commercial Operation.
3.9.1 3.10.1 The WtE Developer shall give a written notice to the concerned SLDC and DISCOM, at least sixty (60) days in advance to the date on which it intends to synchronize the Project to the grid system.
3.9.2 3.10.2 The Project may be synchronized by the WtE Developer to the grid system when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the grid system.
3.9.3 3.10.3 The synchronization equipment shall be installed by the WtE Developer at its generation facility of the Project at its own cost. The WtE Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/grid system and checking/verification is made by the concerned authorities of the grid system.
3.9.4 3.10.4 The WtE Developer shall immediately after synchronization/ tripping of generator, inform the sub-station of the grid system to which the Project is electrically connected in accordance with applicable Grid Code as amended from time to time.
3.9.5 3.10.5 The WtE Developer shall commission the Project within timelines defined for Scheduled COD as per this Agreement, and any delay of the same is subject to the penalties stated in Clause 10.5 of this Agreement.
Appears in 1 contract
Sources: Power Purchase Agreement
Synchronization, Commissioning and Commercial Operation.
3.9.1 3.11.1 The WtE Mini Hydel Project Developer shall give a written notice to the concerned SLDC and DISCOM, at least sixty (60) days in advance to the date on which it intends to synchronize the Project generating Unit to the grid system.
3.9.2 3.11.2 The Project generating Unit may be synchronized by the WtE Mini Hydel Project Developer to the grid system when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the grid system.
3.9.3 3.11.3 The synchronization equipment shall be installed by the WtE Mini Hydel Project Developer at its generation facility of the Project at its own cost. The WtE Mini Hydel Project Developer shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned sub-station/grid system and checking/verification is made by the concerned authorities of the grid system.
3.9.4 3.11.4 The WtE Mini Hydel Project Developer shall immediately after synchronization/ tripping of generator, inform the sub-station of the grid system to which the Project generating Unit is electrically connected in accordance with applicable Grid Code as amended from time to timeCode.
3.9.5 3.11.5 The WtE Mini Hydel Project Developer shall commission the Project within timelines defined for Scheduled COD as per this Agreement, and any delay of the same is subject to the penalties stated in Clause 10.5 of this Agreement.