Common use of System Upgrade Facilities and System Deliverability Upgrades Clause in Contracts

System Upgrade Facilities and System Deliverability Upgrades. Connecting Transmission OwnerCon Edison shall design, procure, construct, install, and own the System Upgrade Facilities and System Deliverability Upgrades described in Appendix A hereto. The responsibility of the DeveloperCon Edison for costs related to System Upgrade Facilities and System Deliverability Upgrades shall be determined in accordance with the provisions of Attachment S to the ISO OATT.

Appears in 2 contracts

Sources: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement