Taking Over. 18.1. The VPN Part of the System shall be taken over and a Taking-Over-Certificate shall be issued by the Purchaser, when it has successfully passed the Acceptance Tests. 18.2. The PPS Part of the System shall be taken over and a Taking-Over-Certificate shall be issued by the Purchaser when it has successfully passed the PPS Acceptance Tests. 18.3. Taking-Over Certificate shall be issued by the Purchaser not later than the second Business day following the day when the Acceptance Tests and/or PPS Acceptance Test has been successfully passed and delivered to the Supplier the same day. The period between the announcement for Ready for Acceptance Tests and Issuance of Taking Over Certificate shall be 6 weeks in principal, however, in no case shall exceed 3 months. 18.4. The Purchaser shall not commercially use any Part of the System before a Taking-Over Certificate has been issued in respect thereof. . -------------------------------------------------------------------------------- EuroTel Bratislava Page 32 of 59 Siemens 13 august-2001 > The Purchaser is allowed to use both Parts of the System for the business simulations which use shall not be deemed as a (i) beginning of the commercial use of the respective Part of the System, Service and Functionalities and/or (ii) Taking over of the System or respective Part of the System. Any Part of the System shall not be deemed taken over unless it is supplied in a manner that all of the Service and Functionalities operate in compliance with the operation description set forth in this Contract.
Appears in 1 contract
Taking Over. 18.1. The VPN Part of the System shall be taken over and a Taking-Over-Certificate shall be issued by the Purchaser, when it has successfully passed the Acceptance Tests.
18.2. The PPS Part of the System shall be taken over and a Taking-Over-Certificate shall be issued by the Purchaser when it has successfully passed the PPS Acceptance Tests.
18.3. Taking-Over Certificate shall be issued by the Purchaser not later than the second Business day following the day when the Acceptance Tests and/or PPS Acceptance Test has been successfully passed and delivered to the Supplier the same day. The period between the announcement for Ready for Acceptance Tests and Issuance of Taking Over Certificate shall be 6 weeks in principal, however, in no case shall exceed 3 months.
18.4. The Purchaser shall not commercially use any Part of the System before a Taking-Over Certificate has been issued in respect thereof. . -------------------------------------------------------------------------------- EuroTel Bratislava Page 32 of 59 Siemens 13 august-2001 > The Purchaser is allowed to use both Parts of the System for the business simulations which use shall not be deemed as a (i) beginning of the commercial use of the respective Part of the System, Service and Functionalities and/or (ii) Taking over of the System or respective Part of the System. Any Part of the System shall not be deemed taken over unless it is supplied in a manner that all of the Service and Functionalities operate in compliance with the operation description set forth in this Contract.
Appears in 1 contract