Time and Schedule. 3.1.1 Time is of the essence as to the prosecution of the Subcontract Work. 3.1.2 If requested, the Subcontractor shall provide the Contractor with scheduling information and Subcontractor's proposed schedule for the Subcontract Work. The Contractor may prepare the Schedule of Work for the Project. 3.1.3 Within seven (7) days of receiving the Schedule of the Work and any updates thereto the Subcontractor shall review such and notify the Contractor in writing of Subcontractor’s acceptance or of any revisions the Subcontractor believes should be made. Any agreed upon revisions shall be the basis for a “no cost” Change Order. If the parties cannot agree upon revisions to the Schedule of Work, Contractor may issue a Written Authorization to Proceed pursuant to Paragraph 5.1 directing performance in accordance with the Schedule of Work as provided by Contractor. The Subcontractor’s failure to provide written notice of acceptance or revisions within the seven (7) days shall constitute acceptance by the Subcontractor and a waiver of Subcontractor’s right to assert a claim seeking an extension of the Subcontractor’s time for performance or an adjustment of the Subcontract Price based on objections or revisions later raised by the Subcontractor. 3.1.4 Contractor shall have the right to modify the construction schedule, to suspend, delay or accelerate, in whole or in part, the commencement or execution of Subcontract Work, or vary the sequence thereof, without compensation to the Subcontractor. In the event such a delay or suspension extends the overall time of performance, the time for the Subcontractor to complete its work shall be extended. 3.1.5 The Subcontractor shall commence the Subcontract Work promptly upon notice to proceed. The Subcontractor shall prosecute the Subcontract Work in a prompt and diligent manner as directed by the Contractor and in accordance with the Schedule of Work without hindering the Work of the Contractor or any other subcontractor. The Subcontractor shall
Appears in 3 contracts
Sources: Master Subcontract Agreement, Master Subcontract Agreement, Master Subcontract Agreement
Time and Schedule. 3.1.1 Time is of the essence as to the prosecution of the Subcontract Work.
3.1.2 If requested, the Subcontractor shall provide the Contractor with scheduling information and Subcontractor's proposed schedule for the Subcontract Work. The Contractor may prepare the Schedule of Work for the Project.
3.1.3 Within seven (7) days of receiving the Schedule of the Work and any updates thereto the Subcontractor shall review such and notify the Contractor in writing of Subcontractor’s acceptance or of any revisions the Subcontractor believes should be made. Any agreed upon revisions shall be the basis for a “no cost” Change Order. If the parties cannot agree upon revisions to the Schedule of Work, Contractor may issue a Written Authorization to Proceed pursuant to Paragraph 5.1 directing performance in accordance with the Schedule of Work as provided by Contractor. The Subcontractor’s failure to provide written notice of acceptance or revisions within the seven (7) days shall constitute acceptance by the Subcontractor and a waiver of Subcontractor’s right to assert a claim seeking an extension of the Subcontractor’s time for performance or an adjustment of the Subcontract Price based on objections or revisions later raised by the Subcontractor.
3.1.4 Contractor shall have the right to modify the construction schedule, to suspendincluding suspending, delay delaying or accelerateaccelerating, in whole or in part, the commencement or execution of Subcontract Work, or vary varying the sequence thereof, without compensation to the Subcontractor. In the event such a delay or suspension extends the overall time of performance, the time for the Subcontractor to complete its work shall be extended.
3.1.5 The Subcontractor shall commence the Subcontract Work promptly upon notice to proceed. The Subcontractor shall prosecute the Subcontract Work in a prompt and diligent manner as directed by the Contractor and in accordance with the Schedule of Work without hindering the Work of the Contractor or any other subcontractor. The Subcontractor shallby
Appears in 1 contract
Sources: Master Subcontract Agreement
Time and Schedule. 3.1.1 Time is of the essence as to the prosecution of the Subcontract Work.
3.1.2 If requested, the Subcontractor shall provide the Contractor with scheduling information and Subcontractor's proposed schedule for the Subcontract Work. The Contractor may prepare the Schedule of Work for the Project.
3.1.3 Within seven (7) days of receiving the Schedule of the Work and any updates thereto the Subcontractor shall review such and notify the Contractor in writing of Subcontractor’s acceptance or of any revisions the Subcontractor believes should be made. Any agreed upon revisions shall be the basis for a “no cost” Change Order. If the parties cannot agree upon revisions to the Schedule of Work, Contractor may issue a Written Authorization to Proceed pursuant to Paragraph 5.1 directing performance in accordance with the Schedule of Work as provided by Contractor. The Subcontractor’s failure to provide written notice of acceptance or revisions within the seven (7) days shall constitute acceptance by the Subcontractor and a waiver of Subcontractor’s right to assert a claim seeking an extension of the Subcontractor’s time for performance or an adjustment of the Subcontract Price based on objections or revisions later raised by the Subcontractor.
3.1.4 Contractor shall have the right to modify the construction schedule, to suspendincluding suspending, delay delaying or accelerateaccelerating, in whole or in part, the commencement or execution of Subcontract Work, or vary varying the sequence thereof, without compensation to the Subcontractor. In the event such a delay or suspension extends the overall time of performance, the time for the Subcontractor to complete its work shall be extended.
3.1.5 The Subcontractor shall commence the Subcontract Work promptly upon notice to proceed. The Subcontractor shall prosecute the Subcontract Work in a prompt and diligent manner as directed by the Contractor and in accordance with the Schedule of Work without hindering the Work of the Contractor or any other subcontractor. The Subcontractor shallSAMPLE
Appears in 1 contract
Sources: Master Subcontract Agreement
Time and Schedule. 3.1.1 Time is of the essence as to the prosecution of the Subcontract Work.
3.1.2 If requested, the Subcontractor shall provide the Contractor with scheduling information and Subcontractor's proposed schedule for the Subcontract Work. The Contractor may prepare the Schedule of Work for the Project.
3.1.3 Within seven (7) days of receiving the Schedule of the Work and any updates thereto the Subcontractor shall review such and notify the Contractor in writing of Subcontractor’s acceptance or of any revisions the Subcontractor believes should be made. Any agreed upon revisions shall be the basis for a “no cost” Change Order. If the parties cannot agree upon revisions to the Schedule of Work, Contractor may issue a Written Authorization to Proceed pursuant to Paragraph 5.1 directing performance in accordance with the Schedule of Work as provided by Contractor. The Subcontractor’s failure to provide written notice of acceptance or revisions within the seven (7) days shall constitute acceptance by the Subcontractor and a waiver of Subcontractor’s right to assert a claim seeking an extension of the Subcontractor’s time for performance or an adjustment of the Subcontract Price based on objections or revisions later raised by the Subcontractor.of
3.1.4 Contractor shall have the right to modify the construction schedule, to suspend, delay or accelerate, in whole or in part, the commencement or execution of Subcontract Work, or vary the sequence thereof, without compensation to the Subcontractor. In the event such a delay or suspension extends the overall time of performance, the time for the Subcontractor to complete its work shall be extended.
3.1.5 The Subcontractor shall commence the Subcontract Work promptly upon notice to proceed. The Subcontractor shall prosecute the Subcontract Work in a prompt and diligent manner as directed by the Contractor and in accordance with the Schedule of Work without hindering the Work of the Contractor or any other subcontractor. The Subcontractor shallshall proceed with the Subcontract Work, making all necessary deliveries, so as to make timely progress and complete the same in accordance with the Schedule of Work and as directed by the Contractor. Whenever, in the Contractor's opinion, the Subcontract Work falls behind, through no fault of the Contractor, the Subcontractor shall increase its labor force and/or provide overtime, Saturday, Sunday and/or holiday work, and shall have each of its subcontractors do likewise, all at no additional cost to or compensation from the Contractor, in order to achieve compliance with the Schedule of the Work.
Appears in 1 contract
Sources: Master Subcontract Agreement
Time and Schedule. 3.1.1 Time is of the essence as to the prosecution of the Subcontract Work.
3.1.2 If requested, the Subcontractor shall provide the Contractor with scheduling information and Subcontractor's proposed schedule for the Subcontract Work. The Contractor may prepare the Schedule of Work for the Project.
3.1.3 Within seven (7) days of receiving the Schedule of the Work and any updates thereto the Subcontractor shall review such and notify the Contractor in writing of Subcontractor’s acceptance or of any revisions the Subcontractor believes should be made. Any agreed upon revisions shall be the basis for a “no cost” Change Order. If the parties cannot agree upon revisions to the Schedule of Work, Contractor may issue a Written Authorization to Proceed pursuant to Paragraph 5.1 directing performance in accordance with the Schedule of Work as provided by Contractor. The Subcontractor’s failure to provide written notice of acceptance or revisions within the seven (7) days shall constitute acceptance by the Subcontractor and a waiver of Subcontractor’s right to assert a claim seeking an extension of the Subcontractor’s time for performance or an adjustment of the Subcontract Price based on objections or revisions later raised by the Subcontractor.
3.1.4 Contractor shall have the right to modify the construction schedule, to suspend, delay or accelerate, in whole or in part, the commencement or execution of Subcontract Work, or vary the sequence thereof, without compensation to the Subcontractor. In the event such a delay or suspension extends the overall time of performance, the time for the Subcontractor to complete its work shall be extended.
3.1.5 The Subcontractor shall commence the Subcontract Work promptly upon notice to proceed. The Subcontractor shall prosecute the Subcontract Work in a prompt and diligent manner as directed by the Contractor and in accordance with the Schedule of Work without hindering the Work of the Contractor or any other subcontractor. The Subcontractor shall.
Appears in 1 contract
Sources: Master Subcontract Agreement