Common use of Time Limits on Claims Clause in Contracts

Time Limits on Claims. Claims by either party must be made within twenty-one (21) days after occurrence of the event giving rise to such Claim or within twenty-one (21) days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manner.

Appears in 16 contracts

Sources: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement

Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made initiated by written notice and include all facts and detailed cost data substantiating to the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother party.

Appears in 4 contracts

Sources: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder

Time Limits on Claims. Claims by either party must be made within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claimnotice. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manner.

Appears in 4 contracts

Sources: Construction Contract (Digex Inc/De), Construction Contract (Monarch Casino & Resort Inc), Construction Contract (Symantec Corp)

Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made initiated by written notice to the Architect and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother party.

Appears in 4 contracts

Sources: Construction Contract (Sierra Pacific Resources /Nv/), Lease Agreement (Immunicon Corp), Construction Contract (Empire Resorts Inc)

Time Limits on Claims. Claims by either party must be made within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice. Any change or addition to a previously made Claim shall be made by written notice and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manneraccordance with this subparagraph 3.3.

Appears in 3 contracts

Sources: Architectural Services Agreement, Architectural/Engineering Services Agreement, Architectural/Engineering Services Agreement

Time Limits on Claims. Claims by either party must be made within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice in writing to the Architect and include all facts the other party, and detailed cost data substantiating must identify the Claim. An additional known bases for each Claim made after and the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannernature and amount of the relief sought.

Appears in 2 contracts

Sources: Small Construction Projects Contract, Construction Contract

Time Limits on Claims. Claims by either party must be made within twenty-one (21) 10 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 10 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claimnotice. An additional Claim made after the initial Claim has been implemented resolved by Change Order will not be considered unless submitted in a timely mannervalid.

Appears in 2 contracts

Sources: Contract for Construction Management Services, Contract for Construction Management Services

Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made initiated by written notice containing a brief description thereof to the Architect and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother party.

Appears in 2 contracts

Sources: Agreement Between Owner and Architect (Chukchansi Economic Development Authority), Construction Manager Agreement (Chukchansi Economic Development Authority)

Time Limits on Claims. Claims by either party must be made within twenty-one (21) 10 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 10 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by in writing to the other party, and must identify the known bases for each Claim and the nature and amount of the relief sought. Failure to timely file a written notice and include all facts and detailed cost data substantiating claim constitutes a waiver of the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerclaim.

Appears in 1 contract

Sources: Request for Proposals

Time Limits on Claims. Claims by either party must be made within twenty-one fourteen (2114) days after occurrence of the event giving rise to such Claim or within twenty-one fourteen (2114) days after the claimant first recognizes that a condition exists which the condition giving claimant believes may give rise to the a Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating notice. In the Claim. An additional event a party fails to submit a Claim made after within the initial Claim has been implemented by Change Order will preceding time period, such party shall not be considered unless submitted entitled to an adjustment in a timely mannerthe Guaranteed Maximum Price or the Contract Time in relation to such Claim.

Appears in 1 contract

Sources: Standard Form of Agreement (Windsor Woodmont Black Hawk Resort Corp)

Time Limits on Claims. Claims by either party must be made within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes or should have recognized the condition giving rise to the Claim, whichever is later. Claims must be made by written notice. Any change or addition to a previously made Claim shall be made by written notice and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manneraccordance with this subparagraph 3.3.

Appears in 1 contract

Sources: Continuing Service Contract

Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made initiated by written notice to the Architect, Owner, and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother parties, if any.

Appears in 1 contract

Sources: Construction Contract

Time Limits on Claims. Claims by either party must be made within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim claim or within twenty-one (21) 21 days after the claimant first recognizes recognizes, or reasonably should have recognized, the condition giving rise to the Claimclaim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claim. An additional Claim claim made after the initial Claim claim has been implemented by Change Order change order will not be considered unless submitted in a timely manner.

Appears in 1 contract

Sources: Trade Contractor Agreement

Time Limits on Claims. Claims by either party must be made within twenty-one (21) days after occurrence of the event giving rise to such Claim or within twenty-one (21) days 21 Days after the claimant first recognizes the recognized condition giving rise to the Claim, whichever is later. For Claims must be made by written notice and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by arising out of denied Change Order will not Requests, the event giving rise to such Claim for purposes of this paragraph shall be considered unless submitted in a timely mannerCounty’s denial of the Change Order Request.

Appears in 1 contract

Sources: Disposition and Development Agreement

Time Limits on Claims. Claims by either party must be made within twenty-one (21) 5 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 5 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claimnotice. An additional Claim made after the initial Claim has been implemented resolved by Change Order will not be considered unless submitted in a timely mannervalid.

Appears in 1 contract

Sources: Construction Services Agreement

Time Limits on Claims. Claims by either party before and during construction must be made within twenty-one (21) days after occurrence of the event giving rise to such Claim or within twenty-one (21) days after the claimant first recognizes or reasonably should have recognized the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claimnotice. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manner.

Appears in 1 contract

Sources: Construction Contract (National Instruments Corp /De/)

Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) 14 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 14 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by initiated in written notice and include all facts and detailed cost data substantiating to the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother party.

Appears in 1 contract

Sources: Design Build Agreement (Badger State Ethanol LLC)

Time Limits on Claims. Claims by either party must be made within twenty-one (21) 5 business days after occurrence of the event giving rise to such Claim or within twenty-one (21) 5 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claimnotice. An additional Claim made after the initial Claim has been implemented resolved by Change Order will not be considered unless submitted in a timely mannervalid.

Appears in 1 contract

Sources: Construction Services Agreement

Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) days after occurrence of the event giving rise to such Claim or within twenty-one five (215) days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made initiated by written notice to the Design Professional and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother party.

Appears in 1 contract

Sources: Construction Manager at Risk Agreement