Time Limits on Claims. Claims by either party must be made within twenty-one (21) days after occurrence of the event giving rise to such Claim or within twenty-one (21) days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manner.
Appears in 16 contracts
Sources: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made initiated by written notice and include all facts and detailed cost data substantiating to the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother party.
Appears in 4 contracts
Sources: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
Time Limits on Claims. Claims by either party must be made within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claimnotice. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manner.
Appears in 4 contracts
Sources: Construction Contract (Digex Inc/De), Construction Contract (Monarch Casino & Resort Inc), Construction Contract (Symantec Corp)
Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made initiated by written notice to the Architect and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother party.
Appears in 4 contracts
Sources: Construction Contract (Sierra Pacific Resources /Nv/), Lease Agreement (Immunicon Corp), Construction Contract (Empire Resorts Inc)
Time Limits on Claims. Claims by either party must be made within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice. Any change or addition to a previously made Claim shall be made by written notice and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manneraccordance with this subparagraph 3.3.
Appears in 3 contracts
Sources: Architectural Services Agreement, Architectural/Engineering Services Agreement, Architectural/Engineering Services Agreement
Time Limits on Claims. Claims by either party must be made within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice in writing to the Architect and include all facts the other party, and detailed cost data substantiating must identify the Claim. An additional known bases for each Claim made after and the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannernature and amount of the relief sought.
Appears in 2 contracts
Sources: Small Construction Projects Contract, Construction Contract
Time Limits on Claims. Claims by either party must be made within twenty-one (21) 10 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 10 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claimnotice. An additional Claim made after the initial Claim has been implemented resolved by Change Order will not be considered unless submitted in a timely mannervalid.
Appears in 2 contracts
Sources: Contract for Construction Management Services, Contract for Construction Management Services
Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made initiated by written notice containing a brief description thereof to the Architect and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother party.
Appears in 2 contracts
Sources: Agreement Between Owner and Architect (Chukchansi Economic Development Authority), Construction Manager Agreement (Chukchansi Economic Development Authority)
Time Limits on Claims. Claims by either party must be made within twenty-one (21) 10 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 10 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by in writing to the other party, and must identify the known bases for each Claim and the nature and amount of the relief sought. Failure to timely file a written notice and include all facts and detailed cost data substantiating claim constitutes a waiver of the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerclaim.
Appears in 1 contract
Sources: Request for Proposals
Time Limits on Claims. Claims by either party must be made within twenty-one fourteen (2114) days after occurrence of the event giving rise to such Claim or within twenty-one fourteen (2114) days after the claimant first recognizes that a condition exists which the condition giving claimant believes may give rise to the a Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating notice. In the Claim. An additional event a party fails to submit a Claim made after within the initial Claim has been implemented by Change Order will preceding time period, such party shall not be considered unless submitted entitled to an adjustment in a timely mannerthe Guaranteed Maximum Price or the Contract Time in relation to such Claim.
Appears in 1 contract
Sources: Standard Form of Agreement (Windsor Woodmont Black Hawk Resort Corp)
Time Limits on Claims. Claims by either party must be made within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes or should have recognized the condition giving rise to the Claim, whichever is later. Claims must be made by written notice. Any change or addition to a previously made Claim shall be made by written notice and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manneraccordance with this subparagraph 3.3.
Appears in 1 contract
Sources: Continuing Service Contract
Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made initiated by written notice to the Architect, Owner, and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother parties, if any.
Appears in 1 contract
Sources: Construction Contract
Time Limits on Claims. Claims by either party must be made within twenty-one (21) 21 days after occurrence of the event giving rise to such Claim claim or within twenty-one (21) 21 days after the claimant first recognizes recognizes, or reasonably should have recognized, the condition giving rise to the Claimclaim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claim. An additional Claim claim made after the initial Claim claim has been implemented by Change Order change order will not be considered unless submitted in a timely manner.
Appears in 1 contract
Sources: Trade Contractor Agreement
Time Limits on Claims. Claims by either party must be made within twenty-one (21) days after occurrence of the event giving rise to such Claim or within twenty-one (21) days 21 Days after the claimant first recognizes the recognized condition giving rise to the Claim, whichever is later. For Claims must be made by written notice and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by arising out of denied Change Order will not Requests, the event giving rise to such Claim for purposes of this paragraph shall be considered unless submitted in a timely mannerCounty’s denial of the Change Order Request.
Appears in 1 contract
Time Limits on Claims. Claims by either party must be made within twenty-one (21) 5 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 5 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claimnotice. An additional Claim made after the initial Claim has been implemented resolved by Change Order will not be considered unless submitted in a timely mannervalid.
Appears in 1 contract
Sources: Construction Services Agreement
Time Limits on Claims. Claims by either party before and during construction must be made within twenty-one (21) days after occurrence of the event giving rise to such Claim or within twenty-one (21) days after the claimant first recognizes or reasonably should have recognized the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claimnotice. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely manner.
Appears in 1 contract
Sources: Construction Contract (National Instruments Corp /De/)
Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) 14 days after occurrence of the event giving rise to such Claim or within twenty-one (21) 14 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by initiated in written notice and include all facts and detailed cost data substantiating to the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother party.
Appears in 1 contract
Time Limits on Claims. Claims by either party must be made within twenty-one (21) 5 business days after occurrence of the event giving rise to such Claim or within twenty-one (21) 5 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice and include all facts and detailed cost data substantiating the Claimnotice. An additional Claim made after the initial Claim has been implemented resolved by Change Order will not be considered unless submitted in a timely mannervalid.
Appears in 1 contract
Sources: Construction Services Agreement
Time Limits on Claims. Claims by either party must be made initiated within twenty-one (21) days after occurrence of the event giving rise to such Claim or within twenty-one five (215) days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made initiated by written notice to the Design Professional and include all facts and detailed cost data substantiating the Claim. An additional Claim made after the initial Claim has been implemented by Change Order will not be considered unless submitted in a timely mannerother party.
Appears in 1 contract