TIME OF COMPLETION. 18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER THE CONTRACT DOCUMENTS. IF THE PROJECT IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERM. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE SHALL RESULT IN LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASE. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. 18.2 Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions of the Projects having occupancy priority. 18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor. 18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day. 18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered. 18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee. 18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable. 18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials. 18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path. 18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.
Appears in 4 contracts
Sources: Construction Services Agreement, Construction Services Agreement, Construction Services Agreement
TIME OF COMPLETION. 18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER THE CONTRACT DOCUMENTS. IF THE PROJECT IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERM. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE SHALL RESULT IN LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASE. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH.
18.2 Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions of the Projects having occupancy priority.
18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- Contractor-prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.
Appears in 3 contracts
Sources: Construction Services Agreement, Construction Services Agreement, Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY JULY 31, 2024 AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, viral pandemics resulting in shelter-in-place orders, quarantines, government shutdowns, substantial interruption to air travel, substantial interruptions in supply chains, and other economic by-products caused by the response to an epidemic or pandemic, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 2 contracts
Sources: Construction Services Agreement, Construction Services Agreement
TIME OF COMPLETION. 18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER THE CONTRACT DOCUMENTS. IF THE PROJECT IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERM. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE SHALL RESULT IN LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASE. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH.
18.2 Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions of the Projects having occupancy priority.
18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- Contractor-prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.
Appears in 2 contracts
Sources: Construction Services Agreement, Pre Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY , 2024 AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, viral pandemics resulting in shelter-in-place orders, quarantines, government shutdowns, substantial interruption to air travel, substantial interruptions in supply chains, and other economic by-products caused by the response to an epidemic or pandemic, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY JANUARY , 2027 AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, viral pandemics resulting in shelter-in-place orders, quarantines, government shutdowns, substantial interruption to air travel, substantial interruptions in supply chains, and other economic by-products caused by the response to an epidemic or pandemic, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER THE CONTRACT DOCUMENTS. IF THE PROJECT IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERM. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE SHALL RESULT IN LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASE. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH.
18.2 Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions of the Projects having occupancy priority.
18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, request that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- Contractor-prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY AUGUST 31, 2022 AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto:
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY , 202_ AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, the results of viral pandemics such as shelter-in-place orders, quarantines, government shutdowns, substantial interruption to air travel, substantial interruptions in supply chains, equipment, materials and/or personnel shortages, and other economic by-products caused by the response to an epidemic or pandemic, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER THE CONTRACT DOCUMENTS. IF THE PROJECT IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERM. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE SHALL RESULT IN LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASE. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH.
18.2 Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions of the Projects having occupancy priority.
18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.materials.
18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- Contractor-prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER THE CONTRACT DOCUMENTS. IF THE PROJECT IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERM. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE SHALL RESULT IN LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASE. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH.
18.2 Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions of the Projects having occupancy priority.priority.
18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.encountered.
18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.agents.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY AUGUST , 2025 AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, viral pandemics resulting in shelter-in-place orders, quarantines, government shutdowns, substantial interruption to air travel, substantial interruptions in supply chains, and other economic by-products caused by the response to an epidemic or pandemic, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Site Lease
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY December , 2025 AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, the results of viral pandemics such as shelter-in-place orders, quarantines, government shutdowns, substantial interruption to air travel, substantial interruptions in supply chains, equipment, materials and/or personnel shortages, and other economic by-products caused by the response to an epidemic or pandemic, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION.
18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER THE CONTRACT DOCUMENTS. IF THE PROJECT IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERM. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE SHALL RESULT IN LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASE. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH.
18.2 Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions of the Projects having occupancy priority.
18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER THE CONTRACT DOCUMENTS. IF THE PROJECT IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERM. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE SHALL RESULT IN LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASE. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH.
18.2 Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions of the Projects having occupancy priority.
18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.. The [contractor] has reviewed the Geo Technical report and related recommendations for soil related water intrusion or unforeseen ground water conditions. Signed
18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY , 202_ AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, viral pandemics resulting in shelter-in-place orders, quarantines, government shutdowns, substantial interruption to air travel, substantial interruptions in supply chains, and other economic by-products caused by the response to an epidemic or pandemic, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER THE CONTRACT DOCUMENTS. IF THE PROJECT IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERM. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE SHALL RESULT IN LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASE. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH.
18.2 Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions of the Projects having occupancy priority.
18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.
18.9 Contractor shall not be charged for Liquidated Damages because of any delays in completion of Work which are not the fault or negligence of Contractor or its Subcontractors, arising from Rain Float or Project Float, including acts of God, as defined in Public Contract Code section 7105, acts of enemy, epidemics, pandemics, and quarantine restrictions. Any delays caused by acts of God, as defined in Public Contract Code section 7105, acts of enemy, epidemics, pandemics, quarantine restrictions, Project shutdowns, suspensions, or any orders issued a federal, state, local or other governmental authority (collectively, “Force Majeure Events”) shall be deemed non-compensable excusable delays. Contractor shall within five (5) calendar days of beginning of any such delay notify District in writing of causes of delay; thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing Work when, in its judgment, the findings of fact justify such an extension. Extensions of time shall apply only to that portion of Work affected by delay, and shall not apply to other portions of Work not so affected. An extension of time may only be granted after proper compliance with Article 8.3 requiring preparation and submission of a properly prepared CPM schedule.
Appears in 1 contract
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN COMPLETED BY PURSUANT TO THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. PROVISIONS OF SECTION 5, ABOVE, AS SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY THE DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE DAMAGE. CONTRACTOR HAS OVERSTAYED ITS LEASE TERMSHALL NOT BE ENTITLED TO A BONUS OR INCENTIVE PAYMENT FOR COMPLETING THE PROJECT PRIOR TO . IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1000.00) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS HIS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above is expressly understood and agreed to by the Parties hereto:
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent or tenant of District, by any separate Contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, by lockouts, by fire, by embargoes, by windstorm, by flood, by earthquake, by acts of war or God, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between the Contractor and the District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Schedule, setting forth the expected dates for commencement and completion of each of the various stages of construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (the “Time Schedule”). The Contractor shall submit the master schedule to the District for acceptance and update the master schedule as appropriate on at least a monthly basis. The Contractor shall incorporate the activities of Contractors on the Project and delivery of products requiring long lead time procurement. The Contractor shall also include the District’s occupancy requirements showing portions of the Projects having occupancy priority.
18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, The Contractor shall be entitled to reimbursement responsible for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges providing the extreme importance District with a Schedule of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 Contractor shall not be entitled to additional compensation for delays Values within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.ten
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY NOVEMBER , 2025 AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, viral pandemics resulting in shelter-in-place orders, quarantines, government shutdowns, substantial interruption to air travel, substantial interruptions in supply chains, and other economic by-products caused by the response to an epidemic or pandemic, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY AUGUST 1, 2021 AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 11, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH.
18.2 Within five (5) business days . This Section 11 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, the results of viral pandemics such as shelter-in-place orders, quarantines, government shutdowns, substantial interruption to air travel, substantial interruptions in supply chains, equipment, materials and/or personnel shortages, and other economic by-products caused by the response to an epidemic or pandemic, by changes in public laws, regulations or ordinances enacted after the Project commencement date in of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the District’s Notice to Proceedreasonable control of Contractor, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions aforesaid date for substantial completion of the Projects having occupancy priority.
18.3 Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor. Contractor will only be allowed a time extension for liquidated damagesunusually severe weather if it results in precipitation or other conditions which in the amount, frequency, or duration is in excess of the norm at the location and time of year in question as established by NOAA weather data. A ten (10) year average of the normal seasonal rainfall for the Stanislaus County area, as set forth determined by the National Weather Service, and any resulting “dry-out” time shall not be considered unusually severe weather and therefore will not constitute a reason for a time extension. No less than 22 calendar days will be allotted for in Contractor’s schedule for each winter weather period which is defined as the Agreementmonths, in aggregate of October, November, December, January, February and March. The weather days shall be shown on the Time Schedule and if not used will become float for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are Projects’ use. Contractor will not documented in be allowed a day-for-day weather delay when the Contract Documents or is bid for construction during a period that normally includes inclement weather. A day-for-day extension will only be allowed for those Days in excess of the Due Diligence Documents provided norm. Contractor is expected to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than work seven (7) days following encountering Days per week (if necessary, irrespective of inclement weather), to maintain access, and to protect the unforeseen conditionWork under construction from the effects of inclement weather. After providing written noticeIf the weather is unusually severe in excess of the NOAA data norm and prevents Contractor from beginning work at the usual daily starting time, or prevents Contractor shall test from proceeding with seventy-five percent (75%) of the normal labor and provide District with Test results (unless District choses to test) and shall proceed with Work based equipment force towards completion of the Day’s current controlling item on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowanceaccepted schedule for a period of at least five hours, and if the Unforeseen Allowance crew is exceededdismissed as a result thereof, the District, in its sole Architect/Construction Manager will designate such time as unavoidable delay and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 grant one (1) calendar-day extension. Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. If Contractor submits a request for an extension of time, Contractor shall also submit an analysis of the Time Schedule, which demonstrates the cause for the delay, the length of the delay, and an explanation of why Contractor believes it is entitled to the time extension. Contractor shall also submit documentation, data and a delay analysis showing that the delay could not be avoided or mitigated by revising the Time Schedule. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Failure to submit such analysis will result in Contractor waiving his/her right to obtain any extension of time. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER THE CONTRACT DOCUMENTS. IF THE PROJECT IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERM. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE SHALL RESULT IN LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASE. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH.
18.2 Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions of the Projects having occupancy priority.
18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY , 202_ AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, viral pandemics resulting in shelter-in-place orders, quarantines, government shutdowns, substantial interruption to air travel, substantial interruptions in supply chains, and other economic by-products caused by the response to an epidemic or pandemic, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY , 20 AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto:
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 A. ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. COMPLETED BY JANUARY , 2027 AS SAID CONTRACT TIME DATE MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER CONTRACTOR IS PREVENTED FROM PROCEEDING WITH OR COMPLETING THE CONTRACT DOCUMENTSPROJECT FOR ANY CAUSE DESCRIBED IN THIS SECTION 10, OR AS OTHERWISE AGREED TO IN WRITING BY DISTRICT AND CONTRACTOR. IF THE PROJECT WORK IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERMDAMAGE. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE CONTRACTOR SHALL RESULT IN PAY TO DISTRICT AS FIXED AND LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 OF ONE THOUSAND DOLLARS ($1,000) PER DAY FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETEDCOMPLETED AND ACCEPTED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASEDAMAGES. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH. This Section 10 and the liquidated damages referred to directly above are expressly understood and agreed to by the parties hereto: Contractor’s Initials District’s Initials
B. In the event that the performance and/or completion of the Project is delayed at any time by any act or omission of District or of any employee, agent, or tenant of District, by any separate contractor employed by District, by changes or alterations in the Project not caused by any fault or omission by Contractor, by strikes, lockouts, fire, embargoes, windstorm, flood, earthquake, acts of war or God, the results of viral pandemics such as shelter-in-place orders, quarantines, government shutdowns, substantial interruption to air travel, substantial interruptions in supply chains, equipment, materials and/or personnel shortages, and other economic by-products caused by the response to an epidemic or pandemic, by changes in public laws, regulations or ordinances enacted after the date of execution of this Construction Services Agreement, by acts of public officials not caused by any fault or omission of Contractor, by an inability to obtain materials or equipment not caused by any act or omission of Contractor, or by any other cause beyond the reasonable control of Contractor, the aforesaid date for substantial completion of the Project shall be extended for a period commensurate with the delay. Contractor shall not be charged liquidated damages because of such delays in completion of work or delays otherwise due to unforeseeable causes beyond the control and without the fault or negligence of Contractor.
18.2 C. The term “substantially completed” or “substantial completion” as used herein shall mean completed in such fashion as to enable District, upon performance of any separate work to be done by District under separate contract or by day labor, beneficially to occupy the Project and to commence operation therein, provided such occupancy and use does not substantially interfere with Contractor’s performance of the remainder of the work, as agreed upon between Contractor and District, which may be accomplished prior to the completion of the work.
D. The term “Fully Completed and Accepted,” as used herein, shall mean that all remaining work has been completed in accordance with the Construction Documents and that successful testing, startup, and satisfactory operation of the Project as a total unit has been accomplished in substantial conformance with the Construction Documents.
E. Within five (5) business days after the Project commencement date in the District’s delivery of a Notice to ProceedProceed for the Project, Contractor shall furnish District with a Baseline reasonably detailed CPM (Critical Path) Schedule Master Schedule, setting forth the expected dates for commencement and completion of each of the various stages of Construction to be performed by Contractor pursuant to Article 9this Construction Services Agreement (“Time Schedule”). The Contractor shall submit the Time Schedule to District for acceptance and update the Time Schedule as appropriate on at least a monthly basis. Contractor shall incorporate the activities of contractors on the Project and delivery of products requiring long lead time procurement. Contractor shall also include the District’s occupancy requirements showing portions of the Projects Project having occupancy priority.
18.3 . Contractor shall not be charged responsible for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall a Schedule of Values within ten (10) calendar working days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings issuance of fact thereon shall a Notice to Proceed, which will be final and conclusive on the parties heretoupdated as needed. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further It is specifically acknowledges understood that District will suffer extreme prejudice should Contractor fail in any way utilize said Time Schedule as it is revised from time to comply with this requirement. Failure time to comply with the procedures and time limits established in this Article shall constitute a waiver determine completion dates of such request. Evidence presented by Contractor that District had actual notice various aspects of the time extension request, that District was not prejudiced Project. Tenant Improvement Payments shall be conditioned upon completion of various aspects of the Project as determined by Contractor’s failure the Inspector pursuant to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceablethe Time Schedule and the Schedule of Values.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 F. Contractor shall not be entitled assessed liquidated damages for this Construction Services Agreement and shall not be subject to additional compensation any damages for delays within its control. delay in completion of the Project, when such delay was caused by the failure of District or the owner of the utility to provide for removal or relocation of the existing main or trunkline utility facilities; however, when Contractor is aware that governmental agenciesremoval or relocation of an existing utility has not been provided for, Contractor shall promptly notify District and the utility in writing, so that provision for such as removal or relocation may be made to avoid and minimize any delay which might be caused by the Department of General Servicesfailure to remove or relocate the main or trunkline utility facilities, gas companies, electrical utility companies, water districts and other agencies may have or to approve Contractor- prepared drawings provide for its removal or approve a proposed installationrelocation. In accordance with Section 4215 of the event Government Code, if Contractor, while performing the work on of delays to the Project from such agencies for which Contractor has no controlProject, provided such delays are discovers any existing main or trunkline utility facilities not caused identified by Contractor’s the public agency [District] in the contract plans or any Subcontractor’s acts or omissionsspecifications, Contractor may shall immediately notify the public agency and utility in writing. The public utility, where it is the owner, shall have the sole discretion to perform repairs or relocation work or permit Contractor to do such repairs or relocation work at a reasonable price. Contractor shall be entitled to a time extension for such delays, but shall not be allowed additional compensation compensated for the costs of such delays locating, repairing damage not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior due to the completion failure of Contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the entire Projectplans and specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. A list of work to be completed and corrected by Contractor, if any, Such compensation shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of in accordance with the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; providedextra work provisions set out in Section 9, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agentsabove.
Appears in 1 contract
Sources: Construction Services Agreement
TIME OF COMPLETION. 18.1 ONCE THE DISTRICT HAS ISSUED A NOTICE TO PROCEED, CONTRACTOR SHALL PROCEED WITH THE CONSTRUCTION OF THE PROJECT WITH REASONABLE DILIGENCE. ▇▇▇▇▇▇▇▇▇▇ CONTRACTOR AGREES THAT THE PROJECT WILL BE SUBSTANTIALLY COMPLETE WITHIN THE CALENDAR DAYS DESIGNATED IN ARTICLE 3 FROM THE NOTICE TO PROCEED. SAID CONTRACT TIME MAY BE EXTENDED FOR SUCH PERIODS OF TIME AS ALLOWED UNDER THE CONTRACT DOCUMENTS. IF THE PROJECT IS NOT SUBSTANTIALLY COMPLETED IN ACCORDANCE WITH THE FOREGOING, IT IS UNDERSTOOD THAT THE DISTRICT WILL SUFFER DAMAGE SINCE CONTRACTOR HAS OVERSTAYED ITS LEASE TERM. IT BEING IMPRACTICAL AND INFEASIBLE TO DETERMINE THE AMOUNT OF ACTUAL DAMAGE, IT IS AGREED THAT CONTRACTOR’S EXTENSION OF THE LEASE SHALL RESULT IN LIQUIDATED DAMAGES, AND NOT AS A PENALTY, THE SUM SET FORTH IN ARTICLE 3 FOR EACH CALENDAR DAY OF DELAY UNTIL WORK IS SUBSTANTIALLY COMPLETED. CONTRACTOR AND ITS SURETY SHALL BE LIABLE FOR THE AMOUNT THEREOF. ANY MONEY DUE OR TO BECOME DUE THE CONTRACTOR MAY BE RETAINED BY THE DISTRICT TO COVER SAID LIQUIDATED DAMAGES FOR OVERSTAYING THE LEASE. SHOULD SUCH MONEY NOT BE SUFFICIENT TO COVER SAID LIQUIDATED DAMAGES, THE DISTRICT SHALL HAVE THE RIGHT TO RECOVER THE BALANCE FROM THE CONTRACTOR OR ITS SURETIES, WHO WILL PAY SAID BALANCE FORTHWITH.
18.2 Within five (5) business days after the Project commencement date in the District’s Notice to Proceed, Contractor shall furnish District with a Baseline CPM (Critical Path) Schedule pursuant to Article 9. The Contractor shall include the District’s occupancy requirements showing portions of the Projects having occupancy priority.
18.3 Contractor shall not be charged for liquidated damages, as set forth in the Agreement, for materially differing underground soil conditions than those outlined in the soils report and from hazardous substances that are encountered that are not documented in the Contract Documents or in the Due Diligence Documents provided to Contractor.
18.3.1 In case of encountering such unforeseen conditions noted above, Contractor shall notify the District in writing immediately and no later than seven (7) days following encountering the unforeseen condition. After providing written notice, Contractor shall test and provide District with Test results (unless District choses to test) and shall proceed with Work based on the Test results. A Change Order pursuant to Article 17 shall be submitted. All time and expenses shall be verified with the Inspector or District Designee either on the day the extra work occurs, but no later than 10 am the following business day.
18.3.2 Change Orders associated with approved unforeseen conditions shall be billed as Change Order Work and allocated to the Unforeseen Allowance, and if the Unforeseen Allowance is exceeded, the District, in its sole and absolute discretion, may allocate such costs to the District Contingency to the extent unforeseen conditions as defined in this Article are encountered.
18.4 Contractor shall within ten (10) calendar days of beginning of any such delay notify District in writing of causes of delay. Thereupon District shall ascertain the facts and extent of delay and grant extension of time for completing work when, in its judgment, the findings of fact justify such an extension. District’s findings of fact thereon shall be final and conclusive on the parties hereto. Extension of time shall apply only to that portion of work affected by the delay, and shall not apply to other portions of work not so affected. Contractor agrees that the extension of time granted under this Article shall be its sole and exclusive remedy for the consequences of any delay described above. For any such delay resulting from the actions or inactions of Architect, District, or their officers, agents, and employees, or changes to the scope of the Work which impact the schedule, Contractor shall be entitled to reimbursement for its reasonable additional costs resulting from such delay, but not any additional profit or fee.
18.5 Contractor acknowledges the extreme importance of promptly notifying and thoroughly documenting any request for time extension and further specifically acknowledges that District will suffer extreme prejudice should Contractor fail in any way to comply with this requirement. Failure to comply with the procedures and time limits established in this Article shall constitute a waiver of such request. Evidence presented by Contractor that District had actual notice of the time extension request, that District was not prejudiced by Contractor’s failure to comply with this requirement, and/or that District considered Contractor’s request despite Contractor’s failure to strictly comply with this provision shall not render this requirement unenforceable.
18.6 Contractor is required to order, obtain, and store materials and equipment sufficiently in advance of its work at no additional cost or advance payment from District to assure that there will be no delays. An extension of time will not be granted for a delay caused by a shortage of materials.
18.7 Contractor shall not be entitled to additional compensation for delays within its control. Contractor is aware that governmental agencies, such as the Department of General Services, gas companies, electrical utility companies, water districts and other agencies may have to approve Contractor- Contractor-prepared drawings or approve a proposed installation. In the event of delays to the Project from such agencies for which Contractor has no control, provided such delays are not caused by Contractor’s or any Subcontractor’s acts or omissions, Contractor may be entitled to a time extension for such delays, but shall not be allowed additional compensation for the costs of such delays not impacting the Project’s critical path.
18.8 District reserves the right to occupy any building or portion thereof or use any improvement contemplated by the Contract Documents prior to the completion of the entire Project. A list of work to be completed and corrected by Contractor, if any, shall be prepared and agreed to between District and Contractor before any such occupancy or use. Such occupancy or use shall not operate as an acceptance of any part of the Project but shall start the guaranty-warranty period on the structure or portion thereof so occupied or improvement or equipment so used; provided, however, that such occupancy or use shall not start the guaranty-warranty period as to items appearing on the list of work yet to be completed and corrected or as to structures or improvements (or portions thereof) that are not occupied or used. No such occupancy or use shall be deemed to have occurred unless and until District has given Contractor written notice of its intention to so occupy or use any particular structure or improvement specifying the portion or portions of the structure, improvement or equipment which will be deemed so occupied or used. District and Contractor shall take reasonable steps to obtain the consent of Contractor’s insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse of or reduction of such insurance. Such occupancy or use by District shall relieve Contractor of (and District shall assume) the responsibility for injury or damage to said occupied or used portions of the Project resulting from use by District or the public or from the action of the elements or from any other cause, except injury or damage resulting from the operations, negligence or intentional acts of Contractor, any Subcontractors or materialmen of any tier, or their officers, employees or agents.
Appears in 1 contract