Common use of Time-Only Changes Clause in Contracts

Time-Only Changes. The DB Contractor may request a Change Order for time extensions, subject to the limitations set forth in Section 15.6.3, for additional time for Completion Deadlines, only for the following: A. Force Majeure Events as described in Section 18.2. B. Failure or inability of the District to provide responses to proposed schedules, design submittals or other submittals and matters for which response by the District is required within the time periods indicated in the Contract Documents, so long as such schedules, design submittals, or other submittals and matters meet all of the applicable requirements of the Contract Documents.

Appears in 2 contracts

Sources: Design Build Agreement, Design Build Agreement