Times for Rendering Services. A. The Effective Date of the Task Order and the times for completing services or providing deliverables will be stated in each Task Order. Engineer is authorized to begin rendering services under a Task Order as of the Effective Date of the Task Order. B. If, through no fault of Engineer, such periods of time or dates are changed, or the orderly and continuous progress of Engineer’s services is impaired, or Engineer’s services are delayed or suspended, then the time for completion of Engineer’s services, and the rates and amounts of Engineer’s compensation, shall be adjusted equitably. C. If Owner authorizes changes in the scope, extent, or character of the Specific Project, or Engineer’s services, then the time for completion of Engineer’s services, and the rates and amounts of Engineer’s compensation, shall be adjusted equitably. D. Owner shall make decisions and carry out its other responsibilities in a timely manner so as not to delay the Engineer’s performance of its services.
Appears in 3 contracts
Sources: Professional Services, Professional Services, Professional Services
Times for Rendering Services. A. The Effective Date of the Task Order and the times for completing services or providing deliverables will be stated in each Task Order. Engineer is authorized to begin rendering services under a Task Order as of the Effective Date of the Task Order.
B. If, through no fault of Engineer, such periods of time or dates are changed, or the orderly and continuous progress of Engineer’s services is impaired, or Engineer’s services are delayed or suspended, then the time for completion of Engineer’s services, and the rates and amounts of Engineer’s compensation, shall be adjusted equitably.
C. If Owner authorizes changes in the scope, extent, or character of the Specific Project, or Engineer’s services, then the time for completion of Engineer’s services, and the rates and amounts of Engineer’s compensation, shall be adjusted equitably.
D. Owner shall make decisions and carry out its other responsibilities in a timely manner so as not to delay the Engineer’s performance of its services.services.
Appears in 1 contract
Sources: Owner and Engineer Agreement for Professional Services
Times for Rendering Services. A. The Effective Date of the Task Order and the times for completing performing services or providing deliverables will be stated in each Task Order. Engineer is authorized to begin rendering If no times are so stated, Testing Firm will perform services under and provide deliverables within a Task Order as of the Effective Date of the Task Orderreasonable time.
B. If, through no fault of EngineerTesting Firm, such periods of time or dates are changed, or the orderly and continuous progress of EngineerTesting Firm’s services is impaired, or EngineerTesting Firm’s services are delayed or suspended, then the time for completion of EngineerTesting Firm’s services, and the rates and amounts of EngineerTesting Firm’s compensation, shall be adjusted equitably.
C. If Owner authorizes changes in the scope, extent, or character of the Specific Project, or Engineer’s servicesProject referenced in an executed Task Order, then the time for completion of EngineerTesting Firm’s services, and the rates and amounts of Engineer’s compensation, shall be adjusted equitably.
D. Owner shall make decisions and carry out its other responsibilities in a timely manner so as not to delay the EngineerTesting Firm’s performance of its services.
Appears in 1 contract
Sources: Professional Services