TOTAL PERFORMANCE. D17.1 The Contractor shall achieve Total Performance within ninety (90) consecutive Working Days of the commencement of the Work as specified in D14 or by June 22, 2007 whichever occurs first. D17.2 When the Contractor or the Contract Administrator considers the Work to be totally performed, the Contractor shall arrange, attend and assist in the inspection of the Work with the Contract Administrator for purposes of verifying Total Performance. Any defects or deficiencies in the Work noted during that inspection shall be remedied by the Contractor at the earliest possible instance and the Contract Administrator notified so that the Work can be reinspected. D17.3 The date on which the Work has been certified by the Contract Administrator as being totally performed to the requirements of the Contract through the issue of a certificate of Total Performance is the date on which Total Performance has been achieved.
Appears in 1 contract
Sources: Bid Opportunity
TOTAL PERFORMANCE. D17.1 D20.1 The Contractor shall achieve Total Performance within ninety one hundred fifteen (90115) consecutive Working Days of the commencement of the Work as specified in D14 or by June 2227, 2007 2015 whichever occurs comes first.
D17.2 D20.2 When the Contractor or the Contract Administrator considers the Work to be totally performed, the Contractor shall arrange, attend and assist in the inspection of the Work with the Contract Administrator for purposes of verifying Total Performance. Any defects or deficiencies in the Work noted during that inspection shall be remedied by the Contractor at the earliest possible instance and the Contract Administrator notified so that the Work can be reinspectedre-inspected.
D17.3 D20.3 The date on which the Work has been certified by the Contract Administrator as being totally performed to the requirements of the Contract through the issue of a certificate of Total Performance is the date on which Total Performance has been achieved.
Appears in 1 contract
Sources: Bid Opportunity
TOTAL PERFORMANCE. D17.1 D16.1 The Contractor shall achieve Total Performance within ninety sixty (9060) consecutive Working Days of the commencement of the Work as specified in D14 or by D13. Notwithstanding the above, the Contractor shall achieve Total Performance no later than June 2215, 2007 whichever occurs first2006.
D17.2 D16.2 When the Contractor or the Contract Administrator considers the Work to be totally performed, the Contractor shall arrange, attend and assist in the inspection of the Work with the Contract Administrator for purposes of verifying Total Performance. Any defects or deficiencies in the Work noted during that inspection shall be remedied by the Contractor at the earliest possible instance and the Contract Administrator notified so that the Work can be reinspectedre-inspected.
D17.3 D16.3 The date on which the Work has been certified by the Contract Administrator as being totally performed to the requirements of the Contract through the issue of a certificate of Total Performance is the date on which Total Performance has been achieved.
Appears in 1 contract
Sources: Bid Opportunity